Spare Parts Inventory & Procurement
Maintenance, Repair & Overhaul › MRO Vendor Management · 15 L4 steps · 6 phases · 9 decision gates · Updated 2026-03-19 19:29
📊
Process Flow Diagram (BPMN)
📋
L4 Process Steps
| Step | Step Name | Role / Swim Lane | System | Input | Output | KPI | Dec? | Exc? |
|---|---|---|---|---|---|---|---|---|
Phase 1 1.1 |
Generate rolling parts demand forecast | Materials Planning Engineer | AMOS by Swiss AviationSoftware | Scheduled maintenance plan, fleet utilisation forecast, historical consumption rates | 12-month rolling parts demand forecast by ATA chapter | Forecast accuracy ≥85% vs actual consumption over rolling 90-day window | N | N |
| 1.2 | Calculate reorder points and min/max stock levels | Materials Planning Engineer | AMOS by Swiss AviationSoftware | Demand forecast, supplier lead times, criticality classification, safety stock policy | Updated min/max parameters and reorder point thresholds per part number in AMOS | Stock-out rate <2% for rotables; <5% for expendables on a rolling 30-day basis | N | N |
| 1.3 | Classify parts by criticality — AOG, Critical, Routine | Engineering & Materials Manager | AMOS by Swiss AviationSoftware | ATA chapter structure, MEL/CDL requirements, historical AOG event data | Part criticality classification list; MEL-linked parts flagged as AOG or Critical in AMOS | 100% of MEL-linked part numbers classified as AOG or Critical within AMOS | Y | N |
Phase 2 2.1 |
Identify approved vendors from Qualified Supplier List | Procurement Specialist | SAP Ariba | Part number, OEM manufacturer P/N, criticality classification, QSL in SAP Ariba | Approved vendor shortlist with lead times, pricing history, and performance scores | ≥2 approved vendors per critical part number; QSL review completed annually | Y | N |
| 2.2 | Issue RFQ or generate purchase order to vendor | Procurement Specialist | SAP Ariba / SAP S/4HANA Finance | Approved vendor shortlist, demand quantity, required delivery date, budget authorisation | RFQ responses evaluated and ranked, or confirmed purchase order issued in SAP | PO issuance within 4h of demand trigger for AOG parts; within 5 business days for routine replenishment | Y | Y |
| 2.3 | Validate airworthiness documentation from vendor | Quality Assurance Inspector | AMOS by Swiss AviationSoftware | Vendor-supplied FAA Form 8130-3 or EASA Form 1, Certificate of Conformance | Airworthiness documentation approval or rejection recorded in AMOS; non-conformances raised | 100% of incoming parts accompanied by valid, traceable airworthiness release documentation | Y | Y |
Phase 3 3.1 |
Receive shipment and verify against purchase order | Stores Receiving Clerk | AMOS by Swiss AviationSoftware | Inbound shipment, purchase order, vendor packing list, airworthiness documentation | Goods receipt confirmation; quantity and part number discrepancies logged in AMOS | Receiving accuracy ≥99.5% (quantity and P/N match vs PO) on monthly cycle count | Y | Y |
| 3.2 | Perform incoming quality inspection on received parts | Quality Assurance Inspector | AMOS by Swiss AviationSoftware | Received parts, airworthiness docs, incoming inspection checklist, part specification | Inspection serviceability tag applied (green = serviceable, red = unserviceable); AMOS inspection record | Incoming inspection completed within 4h for AOG-classified parts; within 48h for routine parts | Y | Y |
| 3.3 | Record serviceable parts into AMOS inventory | Stores Receiving Clerk | AMOS by Swiss AviationSoftware | Inspection-passed part, green serviceability tag, airworthiness documents | Part record created in AMOS inventory with bin location, serial/batch number, and financial value | Inventory record accuracy ≥99.8% validated by quarterly AMOS cycle count | N | N |
Phase 4 4.1 |
Store parts per specification and regulatory requirements | Stores Controller | AMOS by Swiss AviationSoftware | Part storage requirements (temperature, humidity, ESD sensitivity, hazmat classification) | Part physically located in compliant bin; AMOS bin location and storage condition record updated | Storage compliance audit pass rate ≥98% at monthly internal stores inspection | N | N |
| 4.2 | Monitor shelf-life and time-controlled items for expiry | Materials Planning Engineer | AMOS by Swiss AviationSoftware | AMOS shelf-life alert reports, part batch/lot expiry dates, storage duration logs | Shelf-life exception report; near-expiry parts flagged in AMOS for priority issue or disposal | Zero serviceable parts issued or installed past expiry date; shelf-life compliance rate 100% | Y | Y |
Phase 5 5.1 |
Issue parts against approved maintenance work orders | Stores Controller | AMOS by Swiss AviationSoftware | Approved work order part request, technician pick ticket, maintenance task card | Parts issued and consumption recorded against work order; AMOS inventory decremented | Pick accuracy ≥99.5%; parts issue turnaround <30 min for AOG work orders | Y | Y |
| 5.2 | Trigger reorder when stock breaches reorder point | Materials Planning Engineer | AMOS by Swiss AviationSoftware | AMOS stock level alert (below reorder point threshold) | Purchase requisition auto-generated and transmitted to SAP Ariba for PO processing | Reorder trigger-to-PO issuance lead time <2 business days for routine; <4h for critical-classified parts | N | N |
Phase 6 6.1 |
Identify and segregate unserviceable and surplus parts | Engineering & Materials Manager | AMOS by Swiss AviationSoftware | Periodic inventory review output, unserviceable tags, surplus stock report from AMOS | Unserviceable and surplus parts list with recommended disposition (repair, return, or scrap) | Unserviceable inventory disposition completed within 90 days of unserviceable tagging | Y | N |
| 6.2 | Process disposal, scrap, or vendor return with credit | Procurement Specialist | SAP Ariba / SAP S/4HANA Finance | Disposition decision, unserviceable part, vendor return authorisation (VRA), warranty claim documentation | Credit note or scrap record; rotable asset removed from AMOS inventory and SAP asset register | Vendor return credit recovery ≥90% of part value for in-warranty components; scrap processing completed within 30 days of disposition decision | N | Y |
📋