Process Flow Diagram (BPMN)

MR-15 BPMN diagram
📋

L4 Process Steps

StepStep NameRole / Swim LaneSystem InputOutputKPIDec?Exc?
Phase 1
1.1
Detect Warranty-Eligible Maintenance Event Line Maintenance Technician AMOS by Swiss AviationSoftware Unscheduled removal, component failure report, or shop finding in AMOS Potential warranty event flag on work order Warranty event capture rate ≥95% of eligible removals N N
1.2 Validate Warranty Coverage Against OEM Contract Warranty & Contracts Analyst SAP Ariba Component part number, serial number, date of manufacture, hours/cycles on wing Coverage determination: in-scope / out-of-scope with contract reference Coverage determination completed within 2 business days of event flag Y N
1.3 Confirm Component Airworthiness History Warranty & Contracts Analyst Boeing Toolbox / CAMP Component serial number, operator-applied ADs, service bulletins, repair history Airworthiness history extract confirming no owner-induced damage voiding coverage History pull completed within 1 business day N Y
Phase 2
2.1
Gather Supporting Work Orders and Borescope Evidence Technical Records Specialist AMOS by Swiss AviationSoftware AMOS work order, shop finding report, borescope images, QA sign-off records Documentation package: work orders, photographs, tear-down report Documentation pack assembled within 5 business days of removal N N
2.2 Assess Documentation Completeness Against OEM Checklist Warranty & Contracts Analyst AMOS by Swiss AviationSoftware OEM warranty submission checklist, assembled documentation package Gap list or complete sign-off for claim package First-time claim submission completeness rate ≥88% Y N
2.3 Build Formal Warranty Claim Package Warranty & Contracts Analyst AMOS by Swiss AviationSoftware Complete documentation set, contract reference, estimated recovery value Formal warranty claim dossier with cover letter and cost quantification Claim value accuracy within ±5% of final settlement N N
Phase 3
3.1
Submit Claim via OEM Vendor Portal Warranty & Contracts Analyst Ramco Aviation Completed claim dossier, OEM-specific portal credentials, part return authorisation (if required) Claim reference number and submission confirmation from OEM portal Claim submitted within 30 days of component removal (OEM SLA compliance) N Y
3.2 Register Claim in Warranty Tracking Register Warranty & Contracts Analyst AMOS by Swiss AviationSoftware OEM claim reference, submission date, recovery value estimate, OEM SLA deadline Warranty claim record with status, owner, and SLA timer in AMOS 100% of submitted claims logged within same business day N N
3.3 Monitor Claim Status and Escalate on SLA Breach Warranty & Contracts Analyst AMOS by Swiss AviationSoftware AMOS SLA timer alerts, OEM portal status updates Escalation email or updated status flag if OEM response overdue OEM response within 30-day SLA for standard claims; escalation triggered within 5 days of breach Y N
Phase 4
4.1
Review OEM Assessment and Determination Warranty & Contracts Analyst AMOS by Swiss AviationSoftware OEM written determination (accept / partial accept / reject), technical rationale Internal review memo: accepted amount vs. claimed amount, variance analysis Claim acceptance rate ≥70% of submitted value Y N
4.2 Escalate Disputed Claims to Commercial Team MRO Commercial Manager SAP Ariba Rejected or partially accepted claim, OEM determination letter, original contract terms Formal dispute letter or escalation to OEM account executive via Ariba correspondence log Dispute initiated within 10 business days of unsatisfactory determination Y N
4.3 Prepare Technical Counter-Evidence Package Warranty & Contracts Analyst Boeing Toolbox / CAMP OEM rejection rationale, component maintenance records, AD compliance evidence Counter-evidence dossier with supplementary airworthiness and compliance data Counter-evidence submitted within 15 business days of dispute initiation N Y
Phase 5
5.1
Process Approved Warranty Credit or Replacement Part MRO Finance Coordinator SAP S/4HANA Finance (FI/CO) OEM approval letter, credit note or replacement part despatch notice SAP credit memo posted to vendor account; or goods receipt for replacement component Credit posted within 5 business days of OEM approval; replacement part receipted against correct maintenance order N N
5.2 Close Claim and Update Warranty Register Warranty & Contracts Analyst AMOS by Swiss AviationSoftware SAP credit memo number or replacement goods receipt, final settlement amount AMOS warranty record closed with actual recovery value, settlement date, and variance note Claim closure within 3 business days of financial settlement; register accuracy ≥99% N N
Phase 6
6.1
Generate Warranty Recovery KPI Dashboard MRO Performance Analyst Tableau / Power BI AMOS warranty register export, SAP credit memo data, claim age data Monthly warranty KPI report: recovery rate, claim cycle time, rejection rate by OEM Report published by 5th business day of each month; warranty recovery rate ≥3.5% of total MRO spend N N
6.2 Analyse Claim Patterns and Trigger Vendor Review MRO Commercial Manager AWS S3 / Redshift 12-month warranty claim dataset, component reliability data, OEM rejection rate trends Vendor performance scorecard; recommendation for contract renegotiation or supplier change Vendor review completed annually; rejection rate per OEM <15%; repeat claim rate on same part number <5% Y N
📋

Process Attributes

Identification

Process IDMR-15
L1 DomainMaintenance, Repair & Overhaul
L2 ProcessMRO Vendor Management
L3 NameWarranty Claim Management
L4 Steps16 across 6 phases
Decision Gates6 (all with iteration loops)
Exceptions3 documented

Swim Lanes (Roles)

Line Maintenance Technician
Warranty & Contracts Analyst
Technical Records Specialist
MRO Commercial Manager
MRO Finance Coordinator
MRO Performance Analyst

Systems & Tools

AMOS by Swiss AviationSoftwareSAP AribaBoeing Toolbox / CAMPRamco AviationSAP S/4HANA Finance (FI/CO)Tableau / Power BIAWS S3 / Redshift

Key Performance Indicators

Detect Warranty-Eligible Maintenance EventWarranty event capture rate ≥95% of eligible removals
Validate Warranty Coverage Against OEM ContractCoverage determination completed within 2 business days of event flag
Confirm Component Airworthiness HistoryHistory pull completed within 1 business day
Gather Supporting Work Orders and Borescope EvidenceDocumentation pack assembled within 5 business days of removal
Assess Documentation Completeness Against OEM ChecklistFirst-time claim submission completeness rate ≥88%
Build Formal Warranty Claim PackageClaim value accuracy within ±5% of final settlement
Submit Claim via OEM Vendor PortalClaim submitted within 30 days of component removal (OEM SLA compliance)
Register Claim in Warranty Tracking Register100% of submitted claims logged within same business day

Airline-Specific Risks & Pain Points

AMOS warranty flag relies on manual technician input; missed flags cause unrecoverable cost leakage when discovery exceeds OEM claim window (typically 90 days)
OEM warranty terms scattered across multiple Ariba contract line items; exclusions for airline-induced damage (e.g. FOD, corrosion) frequently disputed without clear documented threshold
CAMP component records can have gaps when aircraft are acquired from lessors or third-party MROs; incomplete records lead to OEM claim rejection citing unverifiable maintenance history
Borescope images stored outside AMOS in file shares; retrieval is manual and inconsistent — OEMs (CFM, Pratt & Whitney) require image sets in specific DPI/format standards or reject claims on technical grounds
Each OEM (Airbus, CFM, Honeywell, Collins Aerospace) has different checklist formats and portal requirements; maintaining current versions of each OEM's checklist is a manual process with no automated update feed
Labour rate and material cost calculations reference SAP actuals — discrepancies between AMOS work order cost codes and SAP cost centres cause reconciliation errors that delay settlement

Inputs / Outputs

Primary InputUnscheduled removal, component failure report, or shop finding in AMOS
Primary OutputVendor performance scorecard; recommendation for contract renegotiation or supplier change
PreviousMR-14 · Maintenance Cost Control & KPI ReportingNextCS-01 · Financial Planning & Budgeting