NP-SP-15 BPMN diagram
📋

L4 Process Steps

StepStep NameRole / Swim LaneSystem InputOutputKPIDec?Exc?
Phase 1
1.1
Extract competitive schedule & capacity data Network Intelligence Analyst OAG Schedule Analyser Annual planning cycle trigger; prior-year SSIM schedules Competitor capacity matrix by O&D market (seats, frequencies, ASMs) Market coverage: ≥95% of OAG universe validated within 5 business days N N
1.2 Ingest historical O&D traffic & yield data Network Intelligence Analyst Amadeus SkyCAST 3-year rolling MIDT booking data, internal ticket coupon data O&D demand baseline with seasonality indices per market pair Demand model R² ≥0.90 vs actual bookings on back-test N N
1.3 Validate & cleanse market intelligence dataset Senior Network Planner AWS S3 / Redshift OAG capacity matrix, SkyCAST O&D baseline, macroeconomic indices Validated market intelligence dataset approved for modelling Data completeness ≥98% of target O&D pairs before model run Y N
Phase 2
2.1
Generate long-haul & medium-haul demand scenarios Network Strategy Manager Amadeus SkySYM Validated market intelligence dataset; strategic growth targets from CEO brief 3 demand scenarios (base, upside, downside) per O&D market for 3-year horizon Scenario variance within ±15% of base-case for primary markets N N
2.2 Score and rank route opportunities by strategic fit Network Strategy Manager Amadeus SkyCAST 3 demand scenarios, strategic priority filters (geography, alliance fit, connectivity) Ranked route opportunity scorecard (revenue potential, strategic score, competitive intensity) Top-20 route list updated within 2 weeks of scenario generation N N
2.3 Review route shortlist against network strategy guardrails VP Network Planning Tableau / Power BI Ranked route opportunity scorecard, board-approved network strategy KPIs Approved route shortlist (10–30 routes) for feasibility analysis Shortlist approved within 5 business days of scorecard publication Y N
Phase 3
3.1
Run fleet assignment optimisation for shortlisted routes Fleet Planning Analyst Amadeus SkyMAX Approved route shortlist, current fleet plan, aircraft availability calendar Fleet assignment plan with gauge recommendations per route Fleet utilisation uplift ≥2% vs current plan in optimised output N N
3.2 Assess slot & airport capacity constraints Slot Coordinator IATA CRS (Coordinated Reservation System) Fleet assignment plan, IATA WSG slot library for target airports Slot feasibility report (available, historic grandfather, needs application) Slot feasibility assessment completed ≥90 days before IATA scheduling conference Y Y
3.3 Evaluate airport infrastructure & ground handling readiness Airport Development Manager SITA Airport Management System (AMS) Slot feasibility report, proposed frequencies, aircraft gauge Airport readiness assessment (gates, ground handlers, customs, fuelling) Infrastructure gap identified ≥12 months before proposed launch date N Y
3.4 Confirm operational feasibility of candidate routes Senior Network Planner Amadeus SkyWORKS Fleet assignment plan, slot feasibility report, airport readiness assessment Operationally feasible route set confirmed in SkyWORKS schedule editor ≥80% of shortlisted routes confirmed feasible without major constraint Y N
Phase 4
4.1
Build unit revenue & yield forecast per candidate route Revenue Management Analyst Amadeus Revenue Management (NRM / AltéaRM) Confirmed feasible route set, demand scenarios, competitive fare data from ATPCO PRASM and RASM forecast per route across base/upside/downside scenarios RASM forecast accuracy within ±8% of actuals on launched routes (tracked retrospectively) N N
4.2 Model direct operating costs per route Finance Business Partner — Network SAP S/4HANA Finance (FI/CO) Fleet assignment plan (aircraft type, block hours), fuel price assumptions, airport charges schedule CASM breakdown per route (fuel, airport, crew, maintenance, overhead allocation) CASM model completed within 10 business days of receiving fleet assignment input N N
4.3 Assess route contribution margin and breakeven load factor Network Strategy Manager Tableau / Power BI RASM forecast, CASM breakdown, targeted load factor assumptions Route P&L summary with breakeven load factor and payback period Target contribution margin ≥12% in Year 2; breakeven load factor ≤75% Y N
4.4 Aggregate network business case for plan period VP Network Planning AWS S3 / Redshift Individual route P&L summaries, network-level synergy assumptions (feed, connectivity) 3-year network business case document (revenue, cost, EBIT impact) Network EBIT uplift ≥$150M over plan period vs do-nothing baseline N N
Phase 5
5.1
Package strategic plan for governance review Network Strategy Manager Tableau / Power BI Network business case, route scorecard, risk register Executive briefing pack: network strategy summary, investment ask, risk matrix Briefing pack issued ≥5 business days before Network Strategy Committee meeting N N
5.2 Present plan to Network Strategy Committee VP Network Planning Tableau / Power BI Executive briefing pack, committee member pre-read questions Committee decision: approved / approved with conditions / rejected with rationale Committee decision reached in ≤2 review cycles (no more than 1 deferral per plan) Y N
5.3 Publish approved strategic network plan & handoff to scheduling Network Strategy Manager Amadeus SkyWORKS Approved committee decision, final route list with gauge and frequency targets Published strategic network plan loaded into SkyWORKS as planning baseline for Schedule Planning team Plan published in SkyWORKS ≤3 business days after committee approval N Y
📋

Process Attributes

Identification

Process IDNP-SP-15
L1 DomainNetwork Planning & Scheduling
L2 ProcessSchedule Planning
L3 NameStrategic Network Planning
L4 Steps17 across 5 phases
Decision Gates6 (all with iteration loops)
Exceptions3 documented

Swim Lanes (Roles)

Network Intelligence Analyst
Senior Network Planner
Network Strategy Manager
VP Network Planning
Fleet Planning Analyst
Slot Coordinator
Airport Development Manager
Revenue Management Analyst
Finance Business Partner — Network

Systems & Tools

OAG Schedule AnalyserAmadeus SkyCASTAWS S3 / RedshiftAmadeus SkySYMTableau / Power BIAmadeus SkyMAXIATA CRS (Coordinated Reservation System)SITA Airport Management System (AMS)Amadeus SkyWORKSAmadeus Revenue Management (NRM / AltéaRM)SAP S/4HANA Finance (FI/CO)

Key Performance Indicators

Extract competitive schedule & capacity dataMarket coverage: ≥95% of OAG universe validated within 5 business days
Ingest historical O&D traffic & yield dataDemand model R² ≥0.90 vs actual bookings on back-test
Validate & cleanse market intelligence datasetData completeness ≥98% of target O&D pairs before model run
Generate long-haul & medium-haul demand scenariosScenario variance within ±15% of base-case for primary markets
Score and rank route opportunities by strategic fitTop-20 route list updated within 2 weeks of scenario generation
Review route shortlist against network strategy guardrailsShortlist approved within 5 business days of scorecard publication
Run fleet assignment optimisation for shortlisted routesFleet utilisation uplift ≥2% vs current plan in optimised output
Assess slot & airport capacity constraintsSlot feasibility assessment completed ≥90 days before IATA scheduling conference

Airline-Specific Risks & Pain Points

OAG data lags 48–72 hrs for LCC schedule changes; analyst must reconcile against GDS live availability
MIDT coverage drops to ~60% for LCC-heavy markets where GDS penetration is low; distorts baseline
Macro data (GDP, tourism forecasts) sourced from multiple external vendors with inconsistent update cycles
SkySYM scenario runtime scales poorly for networks >500 O&D pairs; overnight batch required for full network runs
Scoring weights for 'strategic fit' are subjective; senior stakeholders override quantitative ranking without documented rationale
No system-enforced guardrail check; planner reliance on manual KPI dashboard review risks missing constraints

Inputs / Outputs

Primary InputAnnual planning cycle trigger; prior-year SSIM schedules
Primary OutputPublished strategic network plan loaded into SkyWORKS as planning baseline for Schedule Planning team
PreviousNP-SP-14 · Competition & Capacity BenchmarkingNextNP-RM-01 · Inventory & Yield Optimization