US Class I Rail Process Wiki Service Design & Network Planning › Terminal Mission Design
🗺 BPMN Process Flow
RR-01-04-01 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-01-04-01
Domain FamilyNETWORK & PLANNING
L1 DomainService Design & Network Planning
L2 Process GroupTerminal Mission Design
TriggerInitiated by a Service Design / Network Planning Analyst upon receiving new business requirements or changes in network conditions.
OutcomeSuccessful completion results in an optimized terminal mission plan that minimizes dwell times, maximizes train speeds, and ensures all regulatory and operational standards are met.
SystemsUnified Plan 2020 NetControl CADx I-ETMS PS Technology (PST) EHMS (Equipment Health Management System) Wabtrax
Regulatory Hooks49 CFR Part 232 GCOR 6.28
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Define Terminal Mission Objectives Service Design / Network Planning Analyst Unified Plan 2020 Business requirements and network conditions Mission objectives document Objective clarity and alignment with business goals Balancing service needs with operational constraints Y N
1.2 Conduct Feasibility Study Service Design / Network Planning Analyst NetControl Mission objectives document Feasibility study report Feasibility analysis completion time Resource availability and technical limitations Y N
1.3 Develop Terminal Layout Plan Service Design / Network Planning Analyst NetControl Feasibility study report Terminal layout plan Layout plan accuracy and completeness Space constraints and equipment compatibility N Y
1.4 Validate Train Schedules Train Dispatcher NetControl / CADx Terminal layout plan Validated train schedules Schedule adherence rate Traffic congestion and schedule conflicts Y N
1.5 Implement Positive Train Control (PTC) Chief Dispatcher I-ETMS Validated train schedules PTC configuration settings PTC implementation compliance rate Technical integration and system reliability N Y
1.6 Assign Crews and Equipment Trainmaster PS Technology (PST) Validated train schedules Crew assignment plan Crew utilization efficiency Labor availability and skill matching Y N
1.7 Monitor Train Performance Control Operator NetControl / CADx Validated train schedules Performance metrics report Train speed and dwell time Real-time data accuracy and system performance N Y
1.8 Review and Adjust Mission Plan Service Design / Network Planning Analyst Unified Plan 2020 Performance metrics report Adjusted mission plan Plan adjustment frequency Continuous improvement and adaptability Y N
1.9 Ensure Regulatory Compliance Service Design / Network Planning Analyst Unified Plan 2020 Mission plan Compliance checklist Regulatory compliance rate Understanding and adhering to complex regulations Y N
1.10 Update Maintenance Schedules Locomotive Engineer EHMS (Equipment Health Management System) Mission plan Maintenance schedule updates Maintenance schedule adherence rate Predictive maintenance and equipment reliability N Y
1.11 Conduct Safety Audits Car Inspector (Carman) Wabtrax Mission plan Safety audit report Audit compliance rate Ensuring safety standards and protocols Y N
1.12 Finalize Mission Plan Service Design / Network Planning Analyst Unified Plan 2020 Safety audit report Finalized mission plan Plan finalization time Coordination and approval processes N Y
📊 KPIs & Risk Register

KPIs

Terminal dwell under 24 hours Train speed above 20 mph Objective clarity and alignment with business goals Feasibility analysis completion time Layout plan accuracy and completeness Schedule adherence rate PTC implementation compliance rate Crew utilization efficiency Plan adjustment frequency Regulatory compliance rate

Key Risks

Air brake test defect released to the road Traffic congestion and schedule conflicts Technical integration and system reliability Labor availability and skill matching Real-time data accuracy and system performance Predictive maintenance and equipment reliability Ensuring safety standards and protocols Coordination and approval processes

Swim Lanes

Service Design / Network Planning Analyst · 1.1, 1.2, 1.3, 1.8, 1.9, 1.12 Train Dispatcher · 1.4 Chief Dispatcher · 1.5 Trainmaster · 1.6 Control Operator · 1.7 Locomotive Engineer · 1.10 Car Inspector (Carman) · 1.11