US Class I Rail Process Wiki Mechanical & Rolling Stock › Locomotive Heavy Overhaul and Shop Operations
🗺 BPMN Process Flow
RR-05-02-03 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-05-02-03
Domain FamilyOPERATIONS
L1 DomainMechanical & Rolling Stock
L2 Process GroupLocomotive Heavy Overhaul and Shop Operations
TriggerDetection of a locomotive requiring heavy overhaul through routine maintenance checks or failure analysis.
OutcomeA fully overhauled and certified locomotive ready to return to service, meeting all safety and performance requirements.
SystemsUmler NetControl Wabtec Modular Control Architecture NEXSYS III-i EHMS TRAIN II
Regulatory Hooks49 CFR Part 231 49 CFR Part 229 AAR Interchange Rules (Rule 88 and related)
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Locomotive Identification and Classification Manager-Locomotive Maintenance Umler Maintenance report from field crew Work order for heavy overhaul Time to identify locomotive < 2 hours Incorrect identification leading to delays Y N
1.2 Locomotive Removal from Service Train Dispatcher NetControl Work order for heavy overhaul Service removal notification Time to remove locomotive < 4 hours Delays in service removal affecting train schedules Y Y
2.1 Locomotive Arrival at Shop Service Operator Wabtec Modular Control Architecture Service removal notification Arrival confirmation Time to arrive at shop < 1 hour Transport delays affecting shop availability N Y
2.2 Initial Inspection and Defect Detection Electrician (locomotive) Wayside defect detector network Arrival confirmation Defect report Number of defects detected < 5 per locomotive Overlooking critical defects Y N
3.1 Component Replacement and Repair Machinist Downing B. Jenks Shop Defect report Repair log Time to complete repairs < 20 hours per locomotive Delays in component availability Y Y
3.2 Locomotive Reassembly and Testing Electrician (locomotive) NEXSYS III-i Repair log Test report Number of reassembly errors < 1 per locomotive Assembly mistakes leading to further repairs Y N
4.1 Air Brake System Test Manager-Mechanical Maintenance EHMS Test report Brake test certification Pass rate of air brake tests > 98% Air brake failures causing safety hazards Y Y
4.2 Final Inspection and Certification Senior Director-System Locomotive Facility Umler Brake test certification Certification of readiness for service Time to certify locomotive < 4 hours Omissions in final inspection Y N
5.1 Locomotive Return to Service Train Dispatcher NetControl Certification of readiness for service Service return notification Time to return locomotive < 2 hours Delays in returning locomotives to service N Y
5.2 Post-Service Review and Documentation Senior Manager-Mechanical Engineering TRAIN II Service return notification Operational review report Number of operational issues identified < 2 per locomotive Neglecting post-service reviews Y N
📊 KPIs & Risk Register

KPIs

Time to identify locomotive < 2 hours Time to remove locomotive < 4 hours Number of defects detected < 5 per locomotive Time to complete repairs < 20 hours per locomotive Pass rate of air brake tests > 98% Time to certify locomotive < 4 hours Time to return locomotive < 2 hours Number of operational issues identified < 2 per locomotive

Key Risks

Air brake test defect released to the road Delays in service removal affecting train schedules Transport delays affecting shop availability Overlooking critical defects Delays in component availability Assembly mistakes leading to further repairs Omissions in final inspection Delays in returning locomotives to service

Swim Lanes

Manager-Locomotive Maintenance · 1.1, 3.1 Train Dispatcher · 1.2, 5.1 Service Operator · 2.1 Electrician (locomotive) · 2.2, 3.2, 4.1 Machinist · 3.1 Senior Director-System Locomotive Facility · 4.2 Senior Manager-Mechanical Engineering · 5.2