US Class I Rail Process Wiki Finance, Revenue Accounting & Procurement › Capital Budgeting and Project Authorization
🗺 BPMN Process Flow
RR-13-05-01 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-13-05-01
Domain FamilyCOMMERCIAL
L1 DomainFinance, Revenue Accounting & Procurement
L2 Process GroupCapital Budgeting and Project Authorization
TriggerInitiation by the Chairman or President and CEO based on strategic needs and market conditions.
OutcomeSuccessful completion results in authorized funding and project implementation plans for new rail infrastructure.
SystemsNetControl I-ETMS Umler TRAIN II CHARM Wabtrax
Regulatory Hooks49 CFR Part 232 GCOR
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Project Proposal Submission Chairman, President and CEO NetControl Project proposal with financial details Approved project proposal for further analysis Proposal approval within 30 days Delays in proposal submission and review Y N
1.2 Financial Analysis Revenue Accountant, Cost Analyst (regulatory costing) TRAIN II, CHARM Approved project proposal Financial analysis report with cost-benefit assessment Completion of financial analysis within 60 days Inaccurate financial projections Y N
1.3 Regulatory Compliance Review Service Design / Network Planning Analyst, VP Network Planning & Operations Umler, GCOR Financial analysis report Compliance review report with regulatory requirements Regulatory compliance check completed within 45 days Non-compliance with regulatory standards Y N
1.4 Stakeholder Consultation Chairman, President and CEO up.com customer portal, AskRail Compliance review report Stakeholder feedback document Stakeholder consultations completed within 30 days Inconsistent stakeholder opinions Y N
1.5 Project Authorization Decision Chairman, President and CEO NetControl Stakeholder feedback document Authorized project plan with budget allocation Project authorization decision made within 15 days Delays in final approval Y N
1.6 Implementation Planning Service Design / Network Planning Analyst, VP Network Planning & Operations NetControl, I-ETMS Authorized project plan Detailed implementation plan with timelines and milestones Implementation planning completed within 60 days Resource allocation issues Y N
1.7 Environmental Impact Assessment Service Design / Network Planning Analyst, VP Network Planning & Operations Wabtrax Detailed implementation plan Environmental impact assessment report Environmental impact assessment completed within 90 days Non-compliance with environmental regulations Y N
1.8 Final Regulatory Approval Service Design / Network Planning Analyst, VP Network Planning & Operations Umler, GCOR Environmental impact assessment report Final regulatory approval document Regulatory approval received within 60 days Delays in obtaining final approvals Y N
1.9 Project Kickoff Meeting Chairman, President and CEO up.com customer portal, AskRail Final regulatory approval document Kickoff meeting minutes with project team Project kickoff meeting held within 10 days Low attendance or poor communication Y N
1.10 Monitoring and Reporting Service Design / Network Planning Analyst, VP Network Planning & Operations NetControl, I-ETMS Project kickoff meeting minutes Regular project progress reports Monthly progress report submission within 15 days Inaccurate reporting Y N
1.11 Risk Management Review Service Design / Network Planning Analyst, VP Network Planning & Operations NetControl, I-ETMS Regular project progress reports Risk management review report with mitigation strategies Quarterly risk management review completed within 30 days Unidentified risks Y N
1.12 Project Closure Chairman, President and CEO NetControl Risk management review report with mitigation strategies Project closure document with final outcomes Project closure completed within 30 days after project completion Incomplete documentation Y N
📊 KPIs & Risk Register

KPIs

Proposal approval within 30 days Completion of financial analysis within 60 days Regulatory compliance check completed within 45 days Stakeholder consultations completed within 30 days Project authorization decision made within 15 days Implementation planning completed within 60 days Environmental impact assessment completed within 90 days Regulatory approval received within 60 days Project kickoff meeting held within 10 days Monthly progress report submission within 15 days Quarterly risk management review completed within 30 days Project closure completed within 30 days after project completion

Key Risks

Non-compliance with regulatory standards Resource allocation issues Non-compliance with environmental regulations Delays in obtaining final approvals Low attendance or poor communication at kickoff meeting Inaccurate reporting Unidentified risks

Swim Lanes

Chairman, President and CEO · 1.1, 1.5, 1.9 Revenue Accountant, Cost Analyst (regulatory costing) · 1.2 Service Design / Network Planning Analyst, VP Network Planning & Operations · 1.3, 1.6, 1.7, 1.8, 1.10, 1.11