US Class I Rail Process Wiki Engineering: Track, Structures & Signals › Grade Crossing Signals and FRA Crossing Inventory
🗺 BPMN Process Flow
RR-06-08-02 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-06-08-02
Domain FamilyOPERATIONS
L1 DomainEngineering: Track, Structures & Signals
L2 Process GroupGrade Crossing Signals and FRA Crossing Inventory
TriggerScheduled monthly inspections or triggered by system alerts indicating potential issues with grade crossing signals.
OutcomeSuccessful completion results in updated inventory records, compliant signal operations, and documented inspection findings to ensure ongoing safety and regulatory compliance.
SystemsNetControl Wabtrax Umler
Regulatory Hooks49 CFR Part 236 49 CFR Part 1180
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Initiate Inspection Schedule Track Supervisor NetControl Monthly inspection schedule Scheduled inspection tasks Inspection coverage rate > 95% Late scheduling affecting operational readiness N Y
1.2 Conduct Initial Inspection Signal Maintainer Wabtrax Scheduled inspection tasks Inspection report Defect detection rate > 80% Manual data entry errors Y N
1.3 Review Inspection Report Track Supervisor NetControl Inspection report Approved inspection findings Report accuracy rate > 90% Inconsistent reporting formats Y N
1.4 Update Inventory Records Track Supervisor Umler Approved inspection findings Updated inventory records Inventory accuracy rate > 98% Outdated inventory data N Y
1.5 Plan Maintenance Actions Track Supervisor NetControl Approved inspection findings Maintenance plan Maintenance completion rate > 95% Resource allocation issues Y N
1.6 Execute Maintenance Actions Signal Maintainer Wabtrax Maintenance plan Maintenance report Maintenance efficiency rate > 85% Equipment downtime N Y
1.7 Review Maintenance Report Track Supervisor NetControl Maintenance report Approved maintenance actions Report accuracy rate > 90% Inconsistent reporting formats Y N
1.8 Update Inventory Records Post-Maintenance Track Supervisor Umler Approved maintenance actions Updated inventory records Inventory accuracy rate > 98% Outdated inventory data N Y
1.9 Conduct Final Inspection Signal Maintainer Wabtrax Approved maintenance actions Final inspection report Defect detection rate > 80% Manual data entry errors Y N
1.10 Review Final Inspection Report Track Supervisor NetControl Final inspection report Approved final inspection findings Report accuracy rate > 90% Inconsistent reporting formats Y N
1.11 Update Inventory Records Post-Final Inspection Track Supervisor Umler Approved final inspection findings Updated inventory records Inventory accuracy rate > 98% Outdated inventory data N Y
1.12 Close Inspection Cycle Track Supervisor NetControl Approved final inspection findings Closed inspection cycle record Cycle closure rate > 95% Delayed cycle closures N Y
📊 KPIs & Risk Register

KPIs

Inspection coverage rate > 95% Defect detection rate > 80% Report accuracy rate > 90% Inventory accuracy rate > 98% Maintenance completion rate > 95% Maintenance efficiency rate > 85% Cycle closure rate > 95%

Key Risks

Non-compliance with FRA regulations Signal failure leading to safety incidents Delayed maintenance affecting operational readiness Data entry errors in inspection reports Outdated inventory data causing mismanagement

Swim Lanes

Track Supervisor · 1.1, 1.3, 1.4, 1.5, 1.7, 1.8, 1.10, 1.11, 1.12 Signal Maintainer · 1.2, 1.6, 1.9