US Class I Rail Process Wiki Dispatching & Train Movement › Enroute Exception Handling (PTC failure, mechanical, weather)
🗺 BPMN Process Flow
RR-02-05-03 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-02-05-03
Domain FamilyNETWORK & PLANNING
L1 DomainDispatching & Train Movement
L2 Process GroupEnroute Exception Handling (PTC failure, mechanical, weather)
TriggerDetection of PTC failure, mechanical fault, or adverse weather condition by the train crew or system monitoring.
OutcomeSafe resolution of the exception with minimal disruption to the railroad's operations.
SystemsNetControl I-ETMS Harriman Dispatching Center (HDC) EHMS TRAIN II
Regulatory Hooks49 CFR Part 232 GCOR 6.28
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Exception Detection and Reporting Locomotive Engineer NetControl Train status data, PTC failure alert, mechanical fault report, weather condition report Incident report to Harriman Dispatching Center Time from exception detection to reporting < 5 minutes Delayed reporting due to system connectivity issues Y N
1.2 Initial Assessment and Decision Train Dispatcher Harriman Dispatching Center (HDC) Incident report, train status data, weather forecast Decision to continue route, reroute, or stop the train Time from reporting to decision < 10 minutes Inaccurate weather data leading to incorrect decisions Y Y
1.3 Communication and Instruction Train Dispatcher NetControl, I-ETMS Decision from step 1.2 Instructions to train crew via radio or digital communication Time from decision to instruction < 2 minutes Communication failure between dispatcher and crew N Y
1.4 Crew Response and Action Locomotive Engineer, Conductor NetControl Instructions from step 1.3 Action taken by crew (e.g., rerouting, stopping) Time from instruction to action < 5 minutes Crew not following instructions due to confusion Y N
1.5 Safety Checks and Inspections Car Inspector (Carman) EHMS, TRAIN II Train status data, crew reports Safety inspection report Time from action to safety check < 15 minutes Inadequate safety checks leading to undetected issues Y Y
1.6 Decision on Further Action Train Dispatcher, Chief Dispatcher Harriman Dispatching Center (HDC) Safety inspection report, train status data Further instructions to crew or decision to clear the train Time from safety check to further action < 10 minutes Delayed decision-making due to incomplete information Y N
1.7 Communication of Final Decision Train Dispatcher NetControl, I-ETMS Decision from step 1.6 Final instructions to train crew via radio or digital communication Time from further action to communication < 2 minutes Communication failure between dispatcher and crew N Y
1.8 Crew Execution of Final Instructions Locomotive Engineer, Conductor NetControl Final instructions from step 1.7 Execution of final actions by crew (e.g., resuming route, clearing the train) Time from communication to execution < 5 minutes Crew not following instructions due to confusion Y N
1.9 Post-Exception Review and Documentation Train Dispatcher, Chief Dispatcher Harriman Dispatching Center (HDC), TRAIN II Final actions taken, train status data Post-exception review report Time from execution to review < 30 minutes Incomplete documentation leading to future issues Y Y
1.10 Update of Train Status and System Train Dispatcher, Control Operator NetControl, I-ETMS Post-exception review report Updated train status in system Time from review to update < 10 minutes System failure during update process N Y
1.11 Notification of Affected Parties Train Dispatcher, Chief Dispatcher NetControl, I-ETMS Updated train status, affected parties list Notifications to affected parties (e.g., customers, other railroads) Time from update to notification < 5 minutes Delayed notifications causing further disruptions Y N
1.12 Closure of Exception Case Train Dispatcher, Chief Dispatcher Harriman Dispatching Center (HDC), TRAIN II Notifications sent, final train status Closed exception case in system Time from notification to closure < 5 minutes System failure during closure process N Y
📊 KPIs & Risk Register

KPIs

Time from exception detection to reporting < 5 minutes Time from reporting to decision < 10 minutes Time from decision to instruction < 2 minutes Time from instruction to action < 5 minutes Time from action to safety check < 15 minutes Time from further action to communication < 2 minutes Time from communication to execution < 5 minutes Time from execution to review < 30 minutes Time from review to update < 10 minutes Time from update to notification < 5 minutes Time from notification to closure < 5 minutes

Key Risks

Air brake test defect released to the road Inaccurate weather data leading to incorrect decisions Communication failure between dispatcher and crew Crew not following instructions due to confusion Inadequate safety checks leading to undetected issues

Swim Lanes

Train Dispatcher · 1.2, 1.3, 1.6, 1.7, 1.9, 1.10, 1.11 Locomotive Engineer · 1.1, 1.4, 1.8 Conductor · 1.1, 1.4, 1.8 Car Inspector (Carman) · 1.5 Chief Dispatcher · 1.6, 1.9, 1.10, 1.11