RR-15 RR-15-01-02 — STB Major Merger Application Process
This process documents the application submission and review stages for a major merger of two US Class I freight railroads, focusing on regulatory compliance, network integration, and operational readiness.
🗺 BPMN Process Flow
Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG
📋 Process Attributes
| Process ID | RR-15-01-02 |
|---|---|
| Domain Family | CORPORATE |
| L1 Domain | Merger & Network Integration |
| L2 Process Group | STB Major Merger Application Process |
| Trigger | Initiation by Chairman/CEO after approval of the merger agreement |
| Outcome | Successful STB Major Merger Application Process completion, leading to regulatory approval and network integration planning. |
| Systems | NetControl I-ETMS Umler EHMS CHARM ISS / SSDX / CHDX Harriman Dispatching Center (HDC) Wayside defect detector network Machine Vision portals |
| Regulatory Hooks | 49 CFR Part 1180 49 CFR Part 232 AAR Interchange Rules (Rule 88 and related) |
📋 L4 Process Steps
| Step | Name | Role | System | Input | Output | KPI | Pain Point / Risk | Decision? | Exception? |
|---|---|---|---|---|---|---|---|---|---|
| 1.1 | Application Preparation | Integration Program Management Office (PMO) lead | NetControl | Merger agreement details, network maps, and operational data | STB Application Draft | Application completeness within 30 days | Data accuracy and completeness | N | Y |
| 1.2 | Regulatory Compliance Review | Chairman/CEO | I-ETMS | STB Application Draft | Compliance Report | Regulatory compliance identified within 10 days | Understanding complex regulatory requirements | Y | N |
| 1.3 | Network Integration Planning | VP Network Planning & Operations | Umler | Compliance Report, network maps | Integration Plan | Plan finalized within 20 days | Coordination of multiple stakeholders | Y | Y |
| 1.4 | Service Design Review | Service Design / Network Planning Analyst | NetControl | Integration Plan | Service Design Document | Design approved within 15 days | Balancing service needs with operational constraints | Y | N |
| 1.5 | Equipment Health Assessment | Locomotive Engineer | EHMS | Integration Plan, equipment list | Health Report | Assessment completed within 7 days | Equipment readiness | N | Y |
| 1.6 | Train Dispatcher Coordination | Train Dispatcher | Harriman Dispatching Center (HDC) | Service Design Document, schedule | Dispatch Schedule | Schedule finalized within 10 days | Scheduling conflicts | Y | N |
| 1.7 | Car Hire Accounting Update | Car Inspector (Carman) | CHARM | Integration Plan, car list | Updated Car Hire Data | Data updated within 5 days | Accurate data entry | N | Y |
| 1.8 | Interline Settlement Review | VP Network Planning & Operations | ISS / SSDX / CHDX | Integration Plan, settlement terms | Settlement Agreement | Agreement signed within 14 days | Negotiating fair terms | Y | N |
| 1.9 | Wayside Defect Detection Review | Track Inspector | Wayside defect detector network | Integration Plan, track data | Defect Report | Report completed within 10 days | Identifying critical defects | Y | N |
| 1.10 | Machine Vision Portal Review | Train Dispatcher | Machine Vision portals | Integration Plan, vision data | Vision Report | Report reviewed within 7 days | Interpreting visual data | N | Y |
| 1.11 | Positive Train Control Integration | Integration Program Management Office (PMO) lead | I-ETMS | Integration Plan, PTC data | PTC Configuration Document | Configuration completed within 15 days | System compatibility | Y | N |
| 1.12 | Final Application Submission | Chairman/CEO | NetControl | All reviewed documents, final plan | STB Application Submission | Submission made within 5 days | Completeness and accuracy | N | Y |
📊 KPIs & Risk Register
KPIs
Application completeness within 30 days Regulatory compliance identified within 10 days Plan finalized within 20 days Design approved within 15 days Assessment completed within 7 days Schedule finalized within 10 days Data updated within 5 days Agreement signed within 14 days Report completed within 10 days Report reviewed within 7 days Configuration completed within 15 days Submission made within 5 days
Key Risks
Regulatory non-compliance leading to delays Network integration issues causing service disruptions Equipment readiness problems affecting operations Scheduling conflicts impacting train movements Inaccurate data entry in car hire accounting
Swim Lanes
Integration Program Management Office (PMO) lead · 1.1, 1.3, 1.4, 1.6, 1.8, 1.10, 1.12 Chairman/CEO · 1.2, 1.12 VP Network Planning & Operations · 1.3, 1.8 Service Design / Network Planning Analyst · 1.4 Locomotive Engineer · 1.5 Train Dispatcher · 1.6, 1.10 Car Inspector (Carman) · 1.7 Track Inspector · 1.9