US Class I Rail Process Wiki Hazardous Materials & Environmental › TIH/PIH Handling and Route Risk Analysis
🗺 BPMN Process Flow
RR-08-02-02 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-08-02-02
Domain FamilyCORPORATE
L1 DomainHazardous Materials & Environmental
L2 Process GroupTIH/PIH Handling and Route Risk Analysis
TriggerReceipt of a TIH/PIH shipment at a terminal or yard
OutcomeSuccessful completion produces a safe and compliant route plan for the hazardous materials shipment, including necessary notifications, risk assessments, and contingency plans.
SystemsAskRail TRANSCAER SERTC NetControl I-ETMS EHMS Wabtrax
Regulatory Hooks49 CFR Part 172 GCOR 6.28
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Initial Notification Hazmat Compliance Officer AskRail TIH/PIH shipment details Notification to TRANSCAER and SERTC Time to notification < 1 hour Delayed notifications can lead to regulatory penalties N Y
1.2 Route Planning Train Dispatcher NetControl TIH/PIH shipment details, route options Optimized route plan Number of alternative routes considered > 3 Inefficient routing can increase dwell times and costs Y N
1.3 Risk Assessment Emergency Response Coordinator TRANSCAER Route plan, environmental data Risk assessment report Risk score < 50 High-risk routes may require additional safety measures Y Y
1.4 Contingency Planning TRANSCAER Regional Coordinator SERTC Risk assessment report Contingency plan Number of contingency scenarios > 2 Insufficient contingencies can lead to operational disruptions N Y
1.5 Equipment Inspection Car Inspector (Carman) EHMS TIH/PIH shipment details, equipment list Inspection report Inspection completion rate > 95% Defective equipment can pose safety risks Y N
1.6 Route Approval VP Network Planning & Operations NetControl Optimized route plan, risk assessment report, contingency plan Approval document Approval time < 4 hours Delays in approval can impact shipment timelines Y Y
1.7 Dispatch Instructions Train Dispatcher I-ETMS Approved route plan, contingency plan Dispatch instructions Instructions accuracy > 98% Incorrect instructions can lead to operational errors N Y
1.8 Monitoring and Reporting Control Operator Wabtrax Dispatch instructions, real-time data Operational report Reporting frequency > 30 minutes Inadequate monitoring can lead to undetected issues Y N
1.9 Post-Dispatch Review Hazmat Compliance Officer AskRail Operational report, feedback Review document Number of issues identified < 2 Undetected issues can lead to safety hazards Y Y
1.10 Feedback Loop Chairman, President and CEO TRANSCAER Review document Improvement plan Number of improvements implemented > 3 Lack of feedback can hinder continuous improvement N Y
1.11 Final Notification Emergency Response Coordinator SERTC Improvement plan, final route details Final notification to stakeholders Notification time < 2 hours Delayed notifications can impact stakeholder trust N Y
1.12 Closeout Train Dispatcher NetControl Final notification, operational data Process closure document Closure time < 30 minutes Delayed closure can lead to administrative delays N Y
📊 KPIs & Risk Register

KPIs

Time to notification < 1 hour Number of alternative routes considered > 3 Risk score < 50 Number of contingency scenarios > 2 Inspection completion rate > 95% Approval time < 4 hours Instructions accuracy > 98% Reporting frequency > 30 minutes Number of issues identified < 2 Number of improvements implemented > 3 Notification time < 2 hours Closure time < 30 minutes

Key Risks

Regulatory non-compliance due to delayed notifications Operational inefficiencies from inadequate routing Safety risks from high-risk routes without proper safety measures Undetected issues leading to operational disruptions Administrative delays from incomplete process closure

Swim Lanes

Hazmat Compliance Officer · 1.1, 1.9, 1.12 Train Dispatcher · 1.2, 1.7 Emergency Response Coordinator · 1.3, 1.11 TRANSCAER Regional Coordinator · 1.4 Car Inspector (Carman) · 1.5 VP Network Planning & Operations · 1.6