📋 Process Attributes
Process IDRR-06-06-03
Domain FamilyOPERATIONS
L1 DomainEngineering: Track, Structures & Signals
L2 Process GroupSignal Design, Installation and Testing
TriggerInitiation by Track Supervisor upon identification of a need for new or updated signaling infrastructure based on maintenance schedules, safety audits, or operational requirements.
OutcomeSuccessful completion results in the installation and certification of new signal systems that meet regulatory standards, improve track safety, and enhance overall train operations.
SystemsNetControl I-ETMS Wabtrax Umler PS Technology FRA Automated Track Inspection Program (ATIP)
Regulatory Hooks49 CFR Part 236 49 CFR Part 1180
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Signal Design Review Track Supervisor NetControl Maintenance schedule, safety audit reports Signal design proposal Design completion within 2 weeks Inadequate data for accurate design Y N
1.2 Approval by Chief Engineer Chief Engineer / VP Engineering Umler Signal design proposal Approved signal design Approval within 3 days Regulatory compliance issues Y N
1.3 Installation Plan Development Track Supervisor NetControl Approved signal design Installation plan Plan development within 1 week Resource allocation conflicts Y N
1.4 Material Procurement Track Supervisor PS Technology Installation plan Procurement order Materials delivered within 2 weeks Supplier delays Y N
1.5 Site Preparation Track Supervisor NetControl Installation plan, procurement order Prepared site Site preparation within 3 days Weather delays N Y
1.6 Signal Installation Signal Maintainer Wabtrax Prepared site, installation plan Installed signals Installation completed within 2 days Technical difficulties Y N
1.7 Signal Testing PTC Field Engineer / PTC Technician I-ETMS, Wabtrax Installed signals Test report Testing completed within 1 day Signal malfunctions Y N
1.8 Certification by Chief Engineer Chief Engineer / VP Engineering Umler Test report Certification document Certification within 2 days Non-compliance issues Y N
1.9 Update Maintenance Schedule Track Supervisor NetControl, Umler Certification document Updated maintenance schedule Schedule update within 1 day Data entry errors N Y
1.10 Training for Crews Track Supervisor PS Technology, CrewPro Certification document Training records Training completed within 2 days Crew availability N Y
1.11 Final Inspection by Roadmaster Roadmaster NetControl, FRA Automated Track Inspection Program (ATIP) Updated maintenance schedule, training records Inspection report Inspection completed within 1 day Inspection discrepancies Y N
1.12 Approval for Operational Use Chief Engineer / VP Engineering Umler Inspection report Operational approval document Approval within 2 days Regulatory hurdles Y N
📊 KPIs & Risk Register

KPIs

Signal design completion within 2 weeks Installation plan development within 1 week Materials delivered within 2 weeks Site preparation within 3 days Installation completed within 2 days Testing completed within 1 day Certification within 2 days Schedule update within 1 day Training completed within 2 days Inspection completed within 1 day

Key Risks

Regulatory non-compliance during design and installation Technical failures in signal installation leading to operational disruptions Weather delays affecting site preparation and installation timelines Crew availability issues impacting training schedules Inspection discrepancies requiring rework

Swim Lanes

Track Supervisor · 1.1, 1.3, 1.4, 1.5, 1.6, 1.9, 1.10 Chief Engineer / VP Engineering · 1.2, 1.8, 1.12 Signal Maintainer · 1.6 PTC Field Engineer / PTC Technician · 1.7 Roadmaster · 1.11