US Class I Rail Process Wiki Finance, Revenue Accounting & Procurement › Capital Budgeting and Project Authorization
🗺 BPMN Process Flow
RR-13-05-02 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-13-05-02
Domain FamilyCOMMERCIAL
L1 DomainFinance, Revenue Accounting & Procurement
L2 Process GroupCapital Budgeting and Project Authorization
TriggerInitiated by a proposal from the Network Planning & Operations department identifying areas requiring investment.
OutcomeSuccessful completion results in authorized funding for the identified rail infrastructure projects.
SystemsNetControl I-ETMS Umler PS Technology Harriman Dispatching Center CHARM
Regulatory Hooks49 CFR Part 232 GCOR 6.28 49 CFR Part 1180 AAR Interchange Rules (Rule 88 and related)
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Proposal Review Service Design / Network Planning Analyst NetControl Project proposal document Reviewed proposal with cost estimates Proposal review time under 30 days Complexity of integrating multiple projects Y N
1.2 Revenue Impact Analysis Revenue Accountant TRAIN II Reviewed proposal with cost estimates Revenue impact analysis report Revenue impact analysis completed within 10 days Accurate forecasting of revenue changes Y Y
1.3 Cost Analysis Cost Analyst (regulatory costing) Umler Revenue impact analysis report Detailed cost analysis document Cost analysis completed within 7 days Inclusion of all regulatory costs Y N
1.4 Regulatory Compliance Check Service Design / Network Planning Analyst I-ETMS Detailed cost analysis document Compliance checklist with regulatory requirements Regulatory compliance check completed within 5 days Understanding and applying all relevant regulations Y Y
1.5 Project Authorization Request VP Network Planning & Operations Harriman Dispatching Center Compliance checklist with regulatory requirements Project authorization request submitted to senior management Authorization request submitted within 3 days Securing approval from multiple stakeholders Y N
1.6 Senior Management Review Chairman, President and CEO PS Technology Project authorization request submitted to senior management Approval or rejection letter Review completed within 10 days Balancing financial and operational priorities Y Y
1.7 Budget Allocation VP Network Planning & Operations NetControl Approval or rejection letter Budget allocation document Budget allocated within 5 days of approval Ensuring sufficient funds for all authorized projects Y N
1.8 Project Implementation Planning Service Design / Network Planning Analyst Umler Budget allocation document Implementation plan with timelines and milestones Implementation plan completed within 7 days Coordinating with multiple departments for implementation Y Y
1.9 Interline Settlement Review Revenue Accountant CHARM Implementation plan with timelines and milestones Interline settlement review report Review completed within 5 days Ensuring accurate interline settlements Y N
1.10 Final Approval and Execution VP Network Planning & Operations Harriman Dispatching Center Interline settlement review report Project execution authorization letter Execution authorized within 3 days of final approval Executing projects without disrupting ongoing operations Y Y
1.11 Project Monitoring Service Design / Network Planning Analyst NetControl Project execution authorization letter Regular project status reports Weekly progress updates Real-time monitoring of project progress N N
1.12 Post-Implementation Review VP Network Planning & Operations Umler Regular project status reports Post-implementation review report Review completed within 30 days after project completion Identifying areas for improvement in future projects Y N
📊 KPIs & Risk Register

KPIs

Proposal review time under 30 days Revenue impact analysis completed within 10 days Cost analysis completed within 7 days Regulatory compliance check completed within 5 days Authorization request submitted within 3 days Review completed within 10 days Budget allocated within 5 days of approval Implementation plan completed within 7 days Interline settlement review completed within 5 days Execution authorized within 3 days of final approval Weekly progress updates Post-implementation review completed within 30 days after project completion

Key Risks

Inaccurate cost estimates leading to budget overruns Non-compliance with regulatory requirements resulting in fines or delays Disruption of ongoing operations during project execution Failure to meet project timelines causing missed opportunities Inadequate interline settlement arrangements affecting revenue

Swim Lanes

Service Design / Network Planning Analyst · 1.1, 1.3, 1.4, 1.8, 1.9, 1.11 Revenue Accountant · 1.2, 1.5, 1.10 Cost Analyst (regulatory costing) · 1.3 VP Network Planning & Operations · 1.5, 1.7, 1.10 Chairman, President and CEO · 1.6