US Class I Rail Process Wiki Mechanical & Rolling Stock › Bad Order Management
🗺 BPMN Process Flow
RR-05-08-02 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-05-08-02
Domain FamilyOPERATIONS
L1 DomainMechanical & Rolling Stock
L2 Process GroupBad Order Management
TriggerDetection of a hot bearing, wheel impact, or acoustic defect by the wayside defect detector network.
OutcomeThe defective rolling stock is repaired or replaced, ensuring safe operation on the railroad network.
SystemsWayside defect detector network Umler NetControl I-ETMS Wabtec Modular Control Architecture PS Technology TRAIN II EHMS
Regulatory Hooks49 CFR Part 232 49 CFR Part 215 AAR Interchange Rules
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Defect Detection Service Operator Wayside defect detector network Defect data from wayside detectors Defect report Detection accuracy rate above 95% False positives leading to unnecessary inspections N Y
1.2 Initial Assessment Manager-Locomotive Maintenance Umler Defect report Assessment report Assessment completion time under 4 hours Inaccurate assessment leading to improper handling Y N
1.3 Priority Assignment Senior Director-System Locomotive Facility NetControl Assessment report Priority level Average priority assignment time under 2 hours Inconsistent priority levels affecting repair timelines Y N
1.4 Shop Assignment Manager-Mechanical Maintenance I-ETMS Priority level Assigned shop and crew details Shop assignment time under 3 hours Overloaded shops leading to delays Y N
1.5 Repair Initiation Electrician (locomotive) Wabtec Modular Control Architecture Assigned shop and crew details Work order Repair initiation time under 1 hour Inadequate inventory leading to delays N Y
1.6 Parts Acquisition Manager-Mechanical Maintenance TRAIN II Work order Parts list Parts acquisition time under 24 hours Supplier delays affecting repair timelines Y N
1.7 Repair Execution Machinist PS Technology Parts list Repair log Repair execution time under 8 hours Complex repairs leading to overruns N Y
1.8 Quality Assurance Manager-Locomotive Maintenance EHMS Repair log QA report QA completion time under 2 hours Defective repairs leading to rework Y N
1.9 Reassignment for Further Repair Senior Director-System Locomotive Facility NetControl QA report Reassignment details Reassignment time under 1 hour Inefficient reassignment processes Y N
1.10 Final Inspection Electrician (locomotive) Wabtec Modular Control Architecture Reassignment details Inspection report Inspection completion time under 2 hours Missed defects leading to unsafe operation N Y
1.11 Release for Service Manager-Mechanical Maintenance Umler Inspection report Service release notification Release time under 30 minutes Delays in releasing repaired units Y N
1.12 Post-Release Monitoring Service Operator Wabtec Modular Control Architecture Service release notification Monitoring report Post-release monitoring duration of 7 days Undetected issues leading to further defects N Y
📊 KPIs & Risk Register

KPIs

Detection accuracy rate above 95% Assessment completion time under 4 hours Average priority assignment time under 2 hours Shop assignment time under 3 hours Repair initiation time under 1 hour Parts acquisition time under 24 hours Repair execution time under 8 hours QA completion time under 2 hours Reassignment time under 1 hour Inspection completion time under 2 hours Release time under 30 minutes Post-release monitoring duration of 7 days

Key Risks

Defective repairs leading to rework Missed defects leading to unsafe operation Delays in releasing repaired units Overloaded shops leading to delays Inefficient reassignment processes

Swim Lanes

Service Operator · 1.1, 1.12 Manager-Locomotive Maintenance · 1.2, 1.3, 1.6, 1.8, 1.9, 1.11 Senior Director-System Locomotive Facility · 1.4 Manager-Mechanical Maintenance · 1.5, 1.7 Electrician (locomotive) · 1.5, 1.7, 1.10