US Class I Rail Process Wiki Engineering: Track, Structures & Signals › Signal Design, Installation and Testing
🗺 BPMN Process Flow
RR-06-06-01 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-06-06-01
Domain FamilyOPERATIONS
L1 DomainEngineering: Track, Structures & Signals
L2 Process GroupSignal Design, Installation and Testing
TriggerInitiation by Track Supervisor upon identification of a need for new or upgraded signaling infrastructure due to safety concerns, increased traffic, or regulatory requirements.
OutcomeSuccessful completion results in the installation and testing of new signal systems that meet all regulatory standards, ensuring safe and reliable train operations.
SystemsNetControl I-ETMS Wabtrax Umler EHMS
Regulatory Hooks49 CFR Part 236, Subpart I 49 CFR Part 1180
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Signal Design Review Chief Engineer / VP Engineering NetControl Track specifications and safety requirements Signal design proposal Design completion within 30 days Meeting stringent regulatory standards Y N
1.2 Obtain Regulatory Approval Chief Engineer / VP Engineering NetControl Signal design proposal Regulatory approval letter Approval received within 60 days Navigating complex regulatory requirements Y N
1.3 Procurement of Signal Components Track Supervisor Umler Approved signal design proposal Signal components order confirmation Components delivered within 90 days Supply chain disruptions Y N
1.4 Site Preparation and Layout Track Supervisor NetControl Signal components order confirmation Site preparation report Preparation completed within 30 days Coordinating with multiple teams Y N
1.5 Signal Installation Signal Maintainer I-ETMS Site preparation report Installation completion report Installation completed within 60 days Technical challenges during installation Y N
1.6 Signal Testing PTC Field Engineer / PTC Technician Wabtrax Installation completion report Testing report Testing completed within 30 days Ensuring signal reliability Y N
1.7 Signal Calibration PTC Field Engineer / PTC Technician I-ETMS Testing report Calibration report Calibration completed within 10 days Achieving precise signal performance Y N
1.8 Final Inspection and Certification Track Supervisor NetControl Calibration report Final inspection report Inspection completed within 7 days Meeting final regulatory standards Y N
1.9 Update Maintenance Records Track Supervisor EHMS Final inspection report Updated maintenance records Records updated within 5 days Accurate record-keeping Y N
1.10 Training for Crews Train Dispatcher NetControl Updated maintenance records Training completion certificates Crews trained within 14 days Effective training programs Y N
1.11 Post-Installation Monitoring Signal Maintainer Wabtrax Training completion certificates Monitoring report Continuous monitoring for 30 days Detecting early failures Y N
1.12 Final Approval and Activation Track Supervisor NetControl Monitoring report Activation order Activation completed within 5 days Scheduling activation without disrupting operations Y N
📊 KPIs & Risk Register

KPIs

Design completion within 30 days Approval received within 60 days Components delivered within 90 days Preparation completed within 30 days Installation completed within 60 days Testing completed within 30 days Calibration completed within 10 days Inspection completed within 7 days Records updated within 5 days Crews trained within 14 days

Key Risks

Regulatory approval delays Supply chain disruptions Technical installation challenges Signal reliability issues Training effectiveness concerns

Swim Lanes

Chief Engineer / VP Engineering · 1.1, 1.2 Track Supervisor · 1.3, 1.4, 1.9 Signal Maintainer · 1.5, 1.6, 1.7, 1.11 PTC Field Engineer / PTC Technician · 1.6, 1.7 Train Dispatcher · 1.10