US Class I Rail Process Wiki Mechanical & Rolling Stock › Locomotive Running Repair & Servicing
🗺 BPMN Process Flow
RR-05-01-02 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-05-01-02
Domain FamilyOPERATIONS
L1 DomainMechanical & Rolling Stock
L2 Process GroupLocomotive Running Repair & Servicing
TriggerDetection of a hot bearing or wheel impact by the wayside defect detector network, or scheduled maintenance cycle.
OutcomeA fully repaired and serviced locomotive is returned to service with all systems operational and compliant with regulatory standards.
SystemsWayside defect detector network Umler NetControl EHMS I-ETMS Wabtec Modular Control Architecture
Regulatory Hooks49 CFR Part 232 49 CFR Part 215 AAR Interchange Rules (Rule 88 and related)
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Defect Detection Notification Train Dispatcher Wayside defect detector network Hot bearing or wheel impact detection data Defect report to the locomotive shop Time from detection to notification < 10 minutes Delayed notification leading to increased risk of derailment N Y
1.2 Initial Assessment Service Operator Umler Defect report Assessment and prioritization of repair tasks Time to complete assessment < 30 minutes Inaccurate assessment leading to incomplete repairs Y N
1.3 Locomotive Removal from Service Train Dispatcher NetControl Assessment and prioritization of repair tasks Service order to remove locomotive from service Time to remove locomotive < 1 hour Delayed removal leading to operational disruptions N Y
1.4 Locomotive Arrival at Shop Service Operator NetControl Service order Confirmation of locomotive arrival Time to arrive at shop < 2 hours Late arrival delaying repair process N Y
1.5 Initial Inspection and Diagnostics Electrician (locomotive) EHMS Confirmation of locomotive arrival Detailed inspection report Time to complete initial inspection < 4 hours Missed issues leading to further damage Y N
1.6 Repair Planning and Scheduling Manager-Locomotive Maintenance Umler Detailed inspection report Repair plan and schedule Time to complete repair planning < 6 hours Inefficient scheduling leading to delays Y N
1.7 Component Replacement and Repair Machinist Wabtec Modular Control Architecture Repair plan and schedule Repaired locomotive components Time to complete component replacement < 8 hours Substandard repairs leading to rework Y N
1.8 Final Inspection and Testing Electrician (locomotive) EHMS Repaired locomotive components Final inspection report Time to complete final inspection < 2 hours Missed issues leading to rework Y N
1.9 Air Brake Test Electrician (locomotive) I-ETMS Final inspection report Air brake test results Pass rate of air brake tests > 95% Failed air brake test leading to locomotive being returned to shop Y Y
1.10 Return to Service Train Dispatcher NetControl Air brake test results Service order to return locomotive to service Time to return to service < 1 hour Delayed return leading to operational disruptions N Y
1.11 Post-Service Monitoring Electrician (locomotive) EHMS Service order to return locomotive to service Monitoring report Number of post-service failures < 1% Post-service failures leading to additional repairs Y N
1.12 Continuous Improvement Senior Manager-Mechanical Engineering Umler Monitoring report Improvement plan Number of process improvements > 3 per month Lack of continuous improvement leading to inefficiencies Y N
📊 KPIs & Risk Register

KPIs

Time from detection to notification < 10 minutes Time to complete assessment < 30 minutes Time to remove locomotive < 1 hour Time to arrive at shop < 2 hours Time to complete initial inspection < 4 hours Time to complete repair planning < 6 hours Time to complete component replacement < 8 hours Time to complete final inspection < 2 hours Pass rate of air brake tests > 95% Time to return to service < 1 hour Number of post-service failures < 1% Number of process improvements > 3 per month

Key Risks

Air brake test defect released to the road Delayed repair causing operational disruptions Substandard repairs leading to rework Failed air brake test leading to locomotive being returned to shop Lack of continuous improvement leading to inefficiencies

Swim Lanes

Train Dispatcher · 1.1, 1.3, 1.10 Service Operator · 1.2, 1.4 Electrician (locomotive) · 1.5, 1.8, 1.9 Machinist · 1.7 Manager-Locomotive Maintenance · 1.6 Senior Manager-Mechanical Engineering · 1.12