RR-06 RR-06-03-03 — Maintenance-of-Way Programs (rail, tie, surfacing gangs)
This process involves the maintenance of rail, tie, and surfacing gangs to ensure safe and efficient track operations. It includes regular inspections, repairs, and improvements to maintain compliance with regulatory standards.
🗺 BPMN Process Flow
Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG
📋 Process Attributes
| Process ID | RR-06-03-03 |
|---|---|
| Domain Family | OPERATIONS |
| L1 Domain | Engineering: Track, Structures & Signals |
| L2 Process Group | Maintenance-of-Way Programs (rail, tie, surfacing gangs) |
| Trigger | Scheduled maintenance cycle or detection of track defects through automated inspection systems. |
| Outcome | A fully maintained and compliant track system ready for use by freight trains. |
| Systems | NetControl I-ETMS Wabtrax FRA Automated Track Inspection Program (ATIP) Umler PS Technology (PST) |
| Regulatory Hooks | 49 CFR Part 213 49 CFR Part 236, Subpart I 49 CFR Part 234 49 CFR Part 1180 |
📋 L4 Process Steps
| Step | Name | Role | System | Input | Output | KPI | Pain Point / Risk | Decision? | Exception? |
|---|---|---|---|---|---|---|---|---|---|
| 1.1 | Track Inspection | Track Supervisor | Wabtrax, FRA Automated Track Inspection Program (ATIP) | Scheduled inspection plan | Inspection report with defects identified | Defect detection rate above 95% | Inaccurate defect identification leading to missed issues. | Y | N |
| 1.2 | Prioritize Defects | Roadmaster | Umler, PS Technology (PST) | Inspection report | Defect prioritization list | Critical defects addressed within 24 hours | Overlooking critical defects that could affect train safety. | Y | N |
| 1.3 | Schedule Maintenance Crews | Track Supervisor | NetControl, I-ETMS | Defect prioritization list | Maintenance schedule | Crew availability rate above 90% | Inefficient crew scheduling leading to delays. | Y | N |
| 1.4 | Perform Rail Maintenance | Assistant Foreman (track) | NetControl, PS Technology (PST) | Maintenance schedule | Work order completion report | Rail replacement rate above 80% | Substandard rail work leading to increased wear and tear. | N | Y |
| 1.5 | Inspect Repaired Rails | Track Inspector | Wabtrax, FRA Automated Track Inspection Program (ATIP) | Work order completion report | Inspection report for repaired rails | Repaired rail quality above 90% | Defective repairs that could compromise track safety. | Y | Y |
| 1.6 | Update Maintenance Records | Track Supervisor | Umler, PS Technology (PST) | Inspection report for repaired rails | Updated maintenance records | Record accuracy above 95% | Inaccurate record-keeping leading to missed maintenance cycles. | N | Y |
| 1.7 | Review Maintenance Effectiveness | Chief Engineer / VP Engineering | NetControl, I-ETMS | Updated maintenance records | Maintenance effectiveness review report | Track condition improvement rate above 75% | Ineffective maintenance strategies leading to increased track degradation. | Y | N |
| 1.8 | Plan Future Maintenance | Track Supervisor | NetControl, I-ETMS | Maintenance effectiveness review report | Future maintenance plan | Planned maintenance coverage above 90% | Inadequate future planning leading to unexpected track failures. | Y | N |
| 1.9 | Coordinate with Other Departments | Track Supervisor | NetControl, I-ETMS | Future maintenance plan | Coordination report | Cross-departmental collaboration rate above 85% | Lack of coordination leading to conflicting maintenance activities. | Y | N |
| 1.10 | Monitor Track Performance | Track Inspector | Wabtrax, FRA Automated Track Inspection Program (ATIP) | Future maintenance plan | Performance monitoring report | Track performance improvement rate above 80% | Poor track performance affecting train operations. | Y | N |
| 1.11 | Adjust Maintenance Strategy | Chief Engineer / VP Engineering | NetControl, I-ETMS | Performance monitoring report | Adjusted maintenance strategy | Strategy effectiveness improvement rate above 70% | Ineffective strategy adjustments leading to continued track issues. | Y | N |
| 1.12 | Report Maintenance Status | Track Supervisor | NetControl, I-ETMS | Adjusted maintenance strategy | Maintenance status report | Status reporting accuracy above 90% | Inaccurate status reports leading to miscommunication. | N | Y |
📊 KPIs & Risk Register
KPIs
Defect detection rate above 95% Critical defects addressed within 24 hours Crew availability rate above 90% Rail replacement rate above 80% Repaired rail quality above 90% Record accuracy above 95% Track condition improvement rate above 75% Planned maintenance coverage above 90% Cross-departmental collaboration rate above 85% Track performance improvement rate above 80% Strategy effectiveness improvement rate above 70% Status reporting accuracy above 90%
Key Risks
Air brake test defect released to the road Substandard rail work leading to increased wear and tear Defective repairs that could compromise track safety Inaccurate record-keeping leading to missed maintenance cycles Ineffective maintenance strategies leading to increased track degradation
Swim Lanes
Track Supervisor · 1.1, 1.3, 1.6, 1.8, 1.9, 1.12 Roadmaster · 1.2 Assistant Foreman (track) · 1.4 Track Inspector · 1.5, 1.10 Chief Engineer / VP Engineering · 1.7, 1.11