US Class I Rail Process Wiki Engineering: Track, Structures & Signals › Maintenance-of-Way Programs (rail, tie, surfacing gangs)
🗺 BPMN Process Flow
RR-06-03-03 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-06-03-03
Domain FamilyOPERATIONS
L1 DomainEngineering: Track, Structures & Signals
L2 Process GroupMaintenance-of-Way Programs (rail, tie, surfacing gangs)
TriggerScheduled maintenance cycle or detection of track defects through automated inspection systems.
OutcomeA fully maintained and compliant track system ready for use by freight trains.
SystemsNetControl I-ETMS Wabtrax FRA Automated Track Inspection Program (ATIP) Umler PS Technology (PST)
Regulatory Hooks49 CFR Part 213 49 CFR Part 236, Subpart I 49 CFR Part 234 49 CFR Part 1180
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Track Inspection Track Supervisor Wabtrax, FRA Automated Track Inspection Program (ATIP) Scheduled inspection plan Inspection report with defects identified Defect detection rate above 95% Inaccurate defect identification leading to missed issues. Y N
1.2 Prioritize Defects Roadmaster Umler, PS Technology (PST) Inspection report Defect prioritization list Critical defects addressed within 24 hours Overlooking critical defects that could affect train safety. Y N
1.3 Schedule Maintenance Crews Track Supervisor NetControl, I-ETMS Defect prioritization list Maintenance schedule Crew availability rate above 90% Inefficient crew scheduling leading to delays. Y N
1.4 Perform Rail Maintenance Assistant Foreman (track) NetControl, PS Technology (PST) Maintenance schedule Work order completion report Rail replacement rate above 80% Substandard rail work leading to increased wear and tear. N Y
1.5 Inspect Repaired Rails Track Inspector Wabtrax, FRA Automated Track Inspection Program (ATIP) Work order completion report Inspection report for repaired rails Repaired rail quality above 90% Defective repairs that could compromise track safety. Y Y
1.6 Update Maintenance Records Track Supervisor Umler, PS Technology (PST) Inspection report for repaired rails Updated maintenance records Record accuracy above 95% Inaccurate record-keeping leading to missed maintenance cycles. N Y
1.7 Review Maintenance Effectiveness Chief Engineer / VP Engineering NetControl, I-ETMS Updated maintenance records Maintenance effectiveness review report Track condition improvement rate above 75% Ineffective maintenance strategies leading to increased track degradation. Y N
1.8 Plan Future Maintenance Track Supervisor NetControl, I-ETMS Maintenance effectiveness review report Future maintenance plan Planned maintenance coverage above 90% Inadequate future planning leading to unexpected track failures. Y N
1.9 Coordinate with Other Departments Track Supervisor NetControl, I-ETMS Future maintenance plan Coordination report Cross-departmental collaboration rate above 85% Lack of coordination leading to conflicting maintenance activities. Y N
1.10 Monitor Track Performance Track Inspector Wabtrax, FRA Automated Track Inspection Program (ATIP) Future maintenance plan Performance monitoring report Track performance improvement rate above 80% Poor track performance affecting train operations. Y N
1.11 Adjust Maintenance Strategy Chief Engineer / VP Engineering NetControl, I-ETMS Performance monitoring report Adjusted maintenance strategy Strategy effectiveness improvement rate above 70% Ineffective strategy adjustments leading to continued track issues. Y N
1.12 Report Maintenance Status Track Supervisor NetControl, I-ETMS Adjusted maintenance strategy Maintenance status report Status reporting accuracy above 90% Inaccurate status reports leading to miscommunication. N Y
📊 KPIs & Risk Register

KPIs

Defect detection rate above 95% Critical defects addressed within 24 hours Crew availability rate above 90% Rail replacement rate above 80% Repaired rail quality above 90% Record accuracy above 95% Track condition improvement rate above 75% Planned maintenance coverage above 90% Cross-departmental collaboration rate above 85% Track performance improvement rate above 80% Strategy effectiveness improvement rate above 70% Status reporting accuracy above 90%

Key Risks

Air brake test defect released to the road Substandard rail work leading to increased wear and tear Defective repairs that could compromise track safety Inaccurate record-keeping leading to missed maintenance cycles Ineffective maintenance strategies leading to increased track degradation

Swim Lanes

Track Supervisor · 1.1, 1.3, 1.6, 1.8, 1.9, 1.12 Roadmaster · 1.2 Assistant Foreman (track) · 1.4 Track Inspector · 1.5, 1.10 Chief Engineer / VP Engineering · 1.7, 1.11