RR-11 RR-11-08-01 — Joint Facilities and Terminal Railroads
This process manages the interline operations at joint facilities and terminal railroads, ensuring seamless interchange of freight cars between different railroad companies while maintaining regulatory compliance and optimizing equipment utilization.
🗺 BPMN Process Flow
Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG
📋 Process Attributes
| Process ID | RR-11-08-01 |
|---|---|
| Domain Family | NETWORK & PLANNING |
| L1 Domain | Interline, Equipment & Car Management |
| L2 Process Group | Joint Facilities and Terminal Railroads |
| Trigger | Receipt of an inbound train from another railroad company with a set of freight cars to be transferred or re-routed within the network. |
| Outcome | Successful transfer and/or re-routing of freight cars, accurate settlement for interline services, and adherence to all relevant regulations and safety standards. |
| Systems | NetControl I-ETMS Umler TRAIN II EHMS Interline Settlement System (ISS) |
| Regulatory Hooks | 49 CFR Part 232 GCOR 6.28 |
📋 L4 Process Steps
| Step | Name | Role | System | Input | Output | KPI | Pain Point / Risk | Decision? | Exception? |
|---|---|---|---|---|---|---|---|---|---|
| 1.1 | Train Arrival Notification | Train Dispatcher | NetControl | Arrival notification from the inbound train | Dispatch order for the inbound train | Train arrival time within 5 minutes of scheduled arrival | Late arrival due to unforeseen circumstances | N | Y |
| 1.2 | Car Inspection | Car Inspector (Carman) | Wabtrax, Wayside defect detector network | Inbound train with freight cars | Inspection report | 100% of cars inspected within 30 minutes | Defective cars not identified promptly | Y | N |
| 1.3 | Car Hire Settlement Request | Car Hire / Interline Settlement Analyst | Interline Settlement System (ISS), Car Hire Data Exchange (CHDX) | Inspection report and dispatch order | Settlement request | Settlement request generated within 1 hour of car inspection completion | Inaccurate settlement data due to errors | N | Y |
| 1.4 | Equipment Registration Update | Equipment Registration / Umler Data Analyst | Umler, TRAIN II | Settlement request and inspection report | Updated equipment registration record | 95% of equipment registrations updated within 2 hours | Delayed updates affecting subsequent operations | Y | N |
| 1.5 | Train Departure Preparation | Yardmaster, Switchman/Switch Foreman | PS Technology (PST), Harriman Dispatching Center (HDC) | Updated equipment registration and settlement request | Departure order for the outbound train | Train departure prepared within 2 hours of receiving the updated data | Preparation delays affecting overall schedule | N | Y |
| 1.6 | Equipment Health Check | Locomotive Engineer, Conductor | EHMS (Equipment Health Management System) | Departure order and updated equipment registration | Health check report | 100% of locomotives health-checked within 30 minutes before departure | Faulty equipment leading to delays | Y | N |
| 1.7 | Train Departure Notification | Train Dispatcher | NetControl, I-ETMS | Health check report and departure order | Departure notification to the next railroad company | Train departure notification sent within 10 minutes of actual departure | Delayed notifications affecting downstream operations | N | Y |
| 1.8 | Settlement Confirmation | Car Hire / Interline Settlement Analyst | Interline Settlement System (ISS), Car Hire Data Exchange (CHDX) | Departure notification and health check report | Settlement confirmation | 90% of settlements confirmed within 2 hours of departure | Financial discrepancies due to errors in settlement | Y | N |
| 1.9 | Post-Departure Review | Service Design / Network Planning Analyst, VP Network Planning & Operations | NetControl, I-ETMS | Settlement confirmation and operational data | Operational review report | 100% of post-departure reviews completed within 24 hours | Incomplete or inaccurate data affecting analysis | N | Y |
| 1.10 | Continuous Improvement Planning | Service Design / Network Planning Analyst, VP Network Planning & Operations | NetControl, I-ETMS | Operational review report and historical data | Improvement plan | 90% of improvement plans implemented within 1 week | Lack of actionable insights from reviews | Y | N |
| 1.11 | Regulatory Compliance Check | Train Dispatcher, Car Inspector (Carman) | Umler, TRAIN II | Operational review report and improvement plan | Compliance check report | 100% of compliance checks completed within 3 days | Non-compliance issues affecting operations | Y | N |
| 1.12 | Final Settlement Adjustment | Car Hire / Interline Settlement Analyst | Interline Settlement System (ISS), Car Hire Data Exchange (CHDX) | Compliance check report and improvement plan | Adjusted settlement | 95% of final settlements adjusted within 1 day | Complex adjustments due to multiple factors | N | Y |
📊 KPIs & Risk Register
KPIs
Train arrival time within 5 minutes of scheduled arrival 100% of cars inspected within 30 minutes Settlement request generated within 1 hour of car inspection completion 95% of equipment registrations updated within 2 hours Train departure prepared within 2 hours of receiving the updated data 100% of locomotives health-checked within 30 minutes before departure Train departure notification sent within 10 minutes of actual departure 90% of settlements confirmed within 2 hours of departure 100% of post-departure reviews completed within 24 hours 90% of improvement plans implemented within 1 week 100% of compliance checks completed within 3 days 95% of final settlements adjusted within 1 day
Key Risks
Air brake test defect released to the road Inaccurate settlement data due to errors Delayed updates affecting subsequent operations Preparation delays affecting overall schedule Faulty equipment leading to delays Delayed notifications affecting downstream operations Financial discrepancies due to errors in settlement Lack of actionable insights from reviews Non-compliance issues affecting operations Complex adjustments due to multiple factors
Swim Lanes
Train Dispatcher · 1.1, 1.5, 1.7 Car Inspector (Carman) · 1.2, 1.6 Car Hire / Interline Settlement Analyst · 1.3, 1.8, 1.12 Equipment Registration / Umler Data Analyst · 1.4 Yardmaster, Switchman/Switch Foreman · 1.5 Locomotive Engineer, Conductor · 1.6 Service Design / Network Planning Analyst, VP Network Planning & Operations · 1.9, 1.10, 1.11