US Class I Rail Process Wiki Dispatching & Train Movement › Emergency & Derailment Dispatch Response
🗺 BPMN Process Flow
RR-02-08-01 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-02-08-01
Domain FamilyNETWORK & PLANNING
L1 DomainDispatching & Train Movement
L2 Process GroupEmergency & Derailment Dispatch Response
TriggerDetection of an emergency or derailment through NetControl/CADx, Harriman Dispatching Center (HDC), or other monitoring systems.
OutcomeSuccessful containment and mitigation of the emergency/derailment incident with no further accidents, adherence to regulatory requirements, and minimal disruption to rail operations.
SystemsNetControl/CADx I-ETMS Umler Wayside defect detector network Machine Vision portals
Regulatory Hooks49 CFR Part 217 49 CFR Part 232
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Initiate Emergency Response Protocol Train Dispatcher NetControl/CADx Emergency notification from monitoring systems Emergency response plan activation Time to initiate response under 5 minutes Delayed detection of the incident Y N
1.2 Notify Relevant Personnel and Authorities Chief Dispatcher NetControl/CADx, I-ETMS Emergency response plan activation Notification to train crews, yardmasters, switchmen, and local authorities Time to notify all relevant parties under 10 minutes Inaccurate notification distribution N Y
1.3 Assess Incident Impact and Safety Risks Train Dispatcher, Control Operator NetControl/CADx, I-ETMS, Umler Real-time data from monitoring systems Incident impact assessment report Time to complete assessment under 15 minutes Inadequate data availability Y N
1.4 Implement Safety Measures and Evacuation Plans Train Dispatcher, Control Operator NetControl/CADx, I-ETMS Incident impact assessment report Safety measures implementation plan Time to implement safety measures under 20 minutes Ineffective communication of safety protocols N Y
1.5 Coordinate with Local Authorities and Emergency Services Chief Dispatcher, Trainmaster NetControl/CADx, I-ETMS Safety measures implementation plan Coordination report with local authorities Time to coordinate with emergency services under 30 minutes Lack of clear communication channels Y N
1.6 Assess Track and Equipment Damage Track Inspector, Car Inspector (Carman) Wayside defect detector network, Machine Vision portals Incident location data Damage assessment report Time to complete track inspection under 1 hour Inaccurate damage assessment Y N
1.7 Plan for Track Repair and Equipment Replacement Train Dispatcher, Control Operator NetControl/CADx, I-ETMS, Umler Damage assessment report Repair and replacement plan Time to develop repair plan under 2 hours Resource allocation issues N Y
1.8 Restore Normal Operations Train Dispatcher, Control Operator NetControl/CADx, I-ETMS Repair and replacement plan Normal operations restoration report Time to restore normal operations under 4 hours Persistent operational disruptions Y N
1.9 Conduct Post-Incident Review and Analysis Train Dispatcher, Control Operator NetControl/CADx, I-ETMS, Umler Normal operations restoration report Post-incident review report Time to complete post-incident review under 1 day Insufficient data for analysis N Y
1.10 Update Emergency Response Plan and Procedures Chief Dispatcher, Trainmaster NetControl/CADx, I-ETMS Post-incident review report Updated emergency response plan Time to update emergency plan under 2 days Resistance to change in procedures Y N
1.11 Communicate with Stakeholders and Customers Train Dispatcher, Control Operator NetControl/CADx, I-ETMS, up.com customer portal Updated emergency response plan Stakeholder communication report Time to communicate with stakeholders under 3 days Inconsistent communication N Y
1.12 Monitor and Report Incident Recovery Progress Train Dispatcher, Control Operator NetControl/CADx, I-ETMS Incident recovery progress data Recovery progress report Time to update recovery status under 1 hour Inadequate monitoring Y N
📊 KPIs & Risk Register

KPIs

Time to initiate response under 5 minutes Time to notify all relevant parties under 10 minutes Time to complete assessment under 15 minutes Time to implement safety measures under 20 minutes Time to coordinate with emergency services under 30 minutes Time to complete track inspection under 1 hour Time to develop repair plan under 2 hours Time to restore normal operations under 4 hours Time to complete post-incident review under 1 day Time to update emergency plan under 2 days Time to communicate with stakeholders under 3 days Time to update recovery status under 1 hour

Key Risks

Inaccurate detection of the incident leading to delayed response Ineffective communication and coordination among teams Inadequate assessment of damage and safety risks Resource allocation issues during repair and replacement Persistent operational disruptions affecting rail service

Swim Lanes

Train Dispatcher · 1.1, 1.2, 1.4, 1.6, 1.8, 1.9, 1.10, 1.11 Chief Dispatcher · 1.3, 1.5 Control Operator · 1.7, 1.12 Track Inspector · 1.6 Car Inspector (Carman) · 1.6