US Class I Rail Process Wiki Merger & Network Integration › Crew District and Dispatch Territory Consolidation
🗺 BPMN Process Flow
RR-15-06-01 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-15-06-01
Domain FamilyCORPORATE
L1 DomainMerger & Network Integration
L2 Process GroupCrew District and Dispatch Territory Consolidation
TriggerApproval from the Chairman/CEO (deal sponsor) for a merger or network integration project.
OutcomeSuccessful consolidation of crew districts and dispatch territories leading to improved operational efficiency, reduced costs, and enhanced safety standards.
SystemsNetControl I-ETMS Umler PS Technology (PST) EHMS (Equipment Health Management System)
Regulatory Hooks49 CFR Part 232 GCOR (General Code of Operating Rules)
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Initiate Consolidation Plan Integration Program Management Office (PMO) lead NetControl Merger & Network Integration proposal Consolidation plan document Plan development time under 30 days Resource allocation for PMO team N Y
1.2 Review and Approve Plan Chairman/CEO (deal sponsor) NetControl Consolidation plan document Approval memo Plan approval within 10 days of submission Stakeholder buy-in and alignment Y N
2.1 Define New Crew Districts Service Design / Network Planning Analyst NetControl Approved consolidation plan New crew district map Number of new districts within 50% of current count Balancing workload across districts Y N
2.2 Assign Crews to New Districts VP Network Planning & Operations PS Technology (PST) New crew district map Crew assignment document Crew reallocation completed within 2 weeks Training and transition support for affected crews N Y
3.1 Redesign Dispatch Territories Train Dispatcher I-ETMS New crew district map Dispatch territory redesign document Territory redesign completed within 4 weeks Ensuring coverage and response times Y N
3.2 Implement New Dispatch Territories Chief Dispatcher I-ETMS Dispatch territory redesign document Updated dispatch schedule New territories operational within 1 week of implementation Coordination with field operations N Y
4.1 Update Equipment Registers Car Inspector (Carman) Umler New crew district map and dispatch territories Updated equipment register Equipment register update completed within 2 weeks Data integrity and accuracy N Y
4.2 Conduct Safety Audits Locomotive Engineer EHMS (Equipment Health Management System) Updated equipment register Safety audit report Audit completion rate above 95% Resource availability for audits Y N
5.1 Monitor and Adjust Operations Control Operator NetControl Safety audit report Operational adjustment plan Adjustment plan implemented within 1 week of audit completion Continuous monitoring and feedback loop Y N
5.2 Review and Report Performance Integration Program Management Office (PMO) lead NetControl Operational adjustment plan Performance report Performance improvement metrics above 10% Benchmarking and performance tracking N Y
6.1 Finalize Consolidation Chairman/CEO (deal sponsor) NetControl Performance report Final consolidation memo Consolidation finalized within 3 months of plan approval Long-term sustainability and scalability Y N
6.2 Document Lessons Learned Integration Program Management Office (PMO) lead NetControl Final consolidation memo Lessons learned document Documentation completed within 1 month of finalization Capturing best practices and knowledge transfer N Y
📊 KPIs & Risk Register

KPIs

Plan development time under 30 days Plan approval within 10 days of submission Number of new districts within 50% of current count Crew reallocation completed within 2 weeks Territory redesign completed within 4 weeks New territories operational within 1 week of implementation Equipment register update completed within 2 weeks Audit completion rate above 95% Adjustment plan implemented within 1 week of audit completion Performance improvement metrics above 10% Consolidation finalized within 3 months of plan approval Documentation completed within 1 month of finalization

Key Risks

Resource allocation for PMO team Stakeholder buy-in and alignment Balancing workload across districts Training and transition support for affected crews Ensuring coverage and response times Coordination with field operations Data integrity and accuracy Resource availability for audits Continuous monitoring and feedback loop Benchmarking and performance tracking Long-term sustainability and scalability Capturing best practices and knowledge transfer

Swim Lanes

Integration Program Management Office (PMO) lead · 1.1, 2.2, 4.1, 5.1, 6.1, 6.2 Chairman/CEO (deal sponsor) · 1.2, 6.1 Service Design / Network Planning Analyst · 2.1 VP Network Planning & Operations · 2.2 Train Dispatcher · 3.1 Chief Dispatcher · 3.2 Car Inspector (Carman) · 4.1 Locomotive Engineer · 4.2 Control Operator · 5.1