RR-06 RR-06-06-02 — Signal Design, Installation and Testing
This process outlines the design, installation, and testing of new signaling systems on a US Class I freight railroad track segment. It ensures compliance with federal regulations and industry standards to enhance safety and operational efficiency.
🗺 BPMN Process Flow
Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG
📋 Process Attributes
| Process ID | RR-06-06-02 |
|---|---|
| Domain Family | OPERATIONS |
| L1 Domain | Engineering: Track, Structures & Signals |
| L2 Process Group | Signal Design, Installation and Testing |
| Trigger | Initiation by Track Supervisor upon identification of a need for new signaling infrastructure due to track expansion or upgrade. |
| Outcome | Successful completion results in the installation and testing of new signaling systems, ensuring they meet all regulatory requirements and are operational. |
| Systems | NetControl I-ETMS Wabtrax PTC Back Office Server (BOS) FRA Automated Track Inspection Program (ATIP) Umler |
| Regulatory Hooks | 49 CFR Part 236, Subpart I 49 CFR Part 1180 |
📋 L4 Process Steps
| Step | Name | Role | System | Input | Output | KPI | Pain Point / Risk | Decision? | Exception? |
|---|---|---|---|---|---|---|---|---|---|
| 1.1 | Signal Design Review | Track Supervisor | NetControl | Design specifications | Approved design document | Time to approval under 2 weeks | Incompatibility with existing track infrastructure | N | Y |
| 1.2 | Signal Installation Planning | Roadmaster | I-ETMS | Approved design document | Installation plan | Plan completion within 3 days | Coordination with other track maintenance activities | N | Y |
| 1.3 | Signal Installation | Signal Maintainer | Wabtrax | Installation plan | Installed signaling equipment | Equipment installation within 2 weeks | Weather delays affecting installation | N | Y |
| 1.4 | Signal Testing Initial | PTC Field Engineer / PTC Technician | PTC Back Office Server (BOS) | Installed signaling equipment | Initial test report | First test within 1 week of installation | Technical issues with new equipment | Y | N |
| 1.5 | Signal Testing Final | Chief Engineer / VP Engineering | FRA Automated Track Inspection Program (ATIP) | Initial test report | Final test approval document | Final testing within 2 weeks of initial test | Regulatory compliance issues | Y | N |
| 1.6 | Signal Integration with Existing Systems | Service Design / Network Planning Analyst | NetControl (service design use) | Final test approval document | Integration plan | Integration plan within 1 week of final testing | Compatibility with existing signaling systems | N | Y |
| 1.7 | Signal System Training | Employee-in-Charge (EIC) | Umler | Integration plan | Training completion certificates | Training completed within 2 weeks of integration | Resource allocation for training sessions | N | Y |
| 1.8 | Signal System Activation | Track Supervisor | PS Technology (PST) | Training completion certificates | Activation report | System activation within 1 week of training | Operational disruptions during activation | Y | N |
| 1.9 | Signal System Monitoring | Signal Maintainer | EHMS (Equipment Health Management System) | Activation report | Monitoring report | Continuous monitoring for 30 days post-activation | Technical failures after activation | N | Y |
| 1.10 | Signal System Evaluation | Chief Engineer / VP Engineering | TRAIN II (Tele Rail Automated Information Network Phase 2) | Monitoring report | Evaluation report | Evaluation completed within 1 month of activation | Performance issues affecting train operations | Y | N |
| 1.11 | Signal System Maintenance Plan | Roadmaster | CHARM (Car Hire Accounting Rate Master) | Evaluation report | Maintenance plan | Plan completion within 2 weeks of evaluation | Resource allocation for maintenance activities | N | Y |
| 1.12 | Signal System Maintenance Execution | Signal Maintainer | Interline Settlement System (ISS) / Switching Settlement Data Exchange (SSDX) / Car Hire Data Exchange (CHDX) | Maintenance plan | Maintenance completion report | Maintenance completed within 1 month of plan approval | Operational disruptions during maintenance | N | Y |
📊 KPIs & Risk Register
KPIs
Time to approval under 2 weeks Plan completion within 3 days Equipment installation within 2 weeks First test within 1 week of installation Final testing within 2 weeks of initial test Integration plan within 1 week of final testing Training completed within 2 weeks of integration System activation within 1 week of training Continuous monitoring for 30 days post-activation Evaluation completed within 1 month of activation
Key Risks
Technical issues with new equipment Regulatory compliance issues Compatibility with existing signaling systems Operational disruptions during activation and maintenance Performance issues affecting train operations
Swim Lanes
Track Supervisor · 1.1, 1.2, 1.8 Roadmaster · 1.2, 1.6, 1.10, 1.11 Signal Maintainer · 1.3, 1.4, 1.9, 1.12 PTC Field Engineer / PTC Technician · 1.4 Chief Engineer / VP Engineering · 1.5, 1.10 Service Design / Network Planning Analyst · 1.6 Employee-in-Charge (EIC) · 1.7