US Class I Rail Process Wiki Merger & Network Integration › Terminal and Gateway Rationalization
🗺 BPMN Process Flow
RR-15-07-01 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-15-07-01
Domain FamilyCORPORATE
L1 DomainMerger & Network Integration
L2 Process GroupTerminal and Gateway Rationalization
TriggerInitiated by the Integration Program Management Office (PMO) lead upon receiving approval from the Chairman/CEO to proceed with terminal and gateway rationalization.
OutcomeSuccessful completion results in streamlined terminal operations, reduced dwell times, improved train speeds, and enhanced network integration.
SystemsNetControl I-ETMS Umler PS Technology EHMS TRAIN II
Regulatory Hooks49 CFR Part 232 GCOR 6.28 49 CFR Part 1180 49 CFR Part 220 49 CFR Part 228
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Assessment of Current Terminal Operations Service Design / Network Planning Analyst NetControl Current terminal operation data Operational assessment report Dwell time reduction target: 10% within first year Inconsistent data collection methods across terminals N N
1.2 Identify Terminal Rationalization Opportunities VP Network Planning & Operations NetControl Operational assessment report Rationalization opportunities report Number of terminals to be rationalized: 5 within first year Lack of historical data for accurate analysis Y N
1.3 Develop Terminal Rationalization Plan Service Design / Network Planning Analyst NetControl Rationalization opportunities report Terminal rationalization plan Plan development time: 3 months Resource allocation constraints N Y
1.4 Obtain Regulatory Approval Chairman/CEO NetControl (service design use) Terminal rationalization plan Regulatory approval letter Approval time: 60 days Complex regulatory requirements Y N
1.5 Implement Terminal Rationalization Integration Program Management Office (PMO) lead NetControl, I-ETMS Terminal rationalization plan and approval letter Implementation report Implementation completion time: 12 months Resistance to change from operational teams N Y
1.6 Monitor and Adjust Operations Train Dispatcher, Control Operator NetControl, I-ETMS Implementation report Operational monitoring report Adjustments required: 5% within first year Dynamic operational challenges Y N
1.7 Review and Optimize Terminal Operations VP Network Planning & Operations NetControl, I-ETMS Operational monitoring report Optimization plan Optimization completion time: 6 months Resource availability for optimization N Y
1.8 Update Terminal Equipment and Systems Chief Dispatcher, Yardmaster NetControl, I-ETMS Optimization plan Equipment update report Equipment update completion time: 3 months Incompatibility issues with existing systems Y N
1.9 Conduct Training for Operational Teams Service Design / Network Planning Analyst NetControl (service design use) Optimization plan and equipment update report Training completion certificate Training time: 2 weeks per team Low training attendance N Y
1.10 Evaluate Terminal Rationalization Impact Integration Program Management Office (PMO) lead NetControl, I-ETMS Training completion certificate Impact evaluation report Dwell time reduction: 15% within first year Measuring the impact of changes Y N
1.11 Report to Stakeholders Chairman/CEO NetControl (service design use) Impact evaluation report Stakeholder report Reporting time: 2 weeks after impact evaluation Stakeholder communication challenges N Y
1.12 Plan for Continuous Improvement VP Network Planning & Operations NetControl, I-ETMS Impact evaluation report and stakeholder report Continuous improvement plan Improvement plan development time: 1 month Identifying areas for ongoing improvements Y N
📊 KPIs & Risk Register

KPIs

Terminal dwell under 24 hours: 90% within first year Train speed above 20 mph: 85% within first year Dwell time reduction target: 10% within first year Number of terminals to be rationalized: 5 within first year Plan development time: 3 months Approval time: 60 days Implementation completion time: 12 months Adjustments required: 5% within first year Optimization completion time: 6 months Equipment update completion time: 3 months Training time: 2 weeks per team Dwell time reduction: 15% within first year Reporting time: 2 weeks after impact evaluation Improvement plan development time: 1 month

Key Risks

Air brake test defect released to the road Regulatory compliance issues during implementation Operational disruptions due to changes Resistance to change from operational teams Incompatibility issues with existing systems

Swim Lanes

Service Design / Network Planning Analyst · 1.1, 1.3, 1.7, 1.9 VP Network Planning & Operations · 1.2, 1.8, 1.11, 1.12 Integration Program Management Office (PMO) lead · 1.4, 1.5, 1.6, 1.10 Chairman/CEO · 1.2, 1.11 Train Dispatcher, Control Operator · 1.6 Chief Dispatcher, Yardmaster · 1.8