US Class I Rail Process Wiki Dispatching & Train Movement › Emergency & Derailment Dispatch Response
🗺 BPMN Process Flow
RR-02-08-02 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-02-08-02
Domain FamilyNETWORK & PLANNING
L1 DomainDispatching & Train Movement
L2 Process GroupEmergency & Derailment Dispatch Response
TriggerDetection of an emergency or derailment by wayside defect detectors, machine vision portals, or direct reports from train crew members.
OutcomeA safe and orderly response to the emergency, ensuring no further incidents occur, securing the derailment site, and initiating recovery and repair operations.
SystemsNetControl CADx Umler EHMS
Regulatory Hooks49 CFR Part 232 GCOR 6.28
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Receive Notification Train Dispatcher NetControl / CADx Derailment notification from wayside defect detector or crew report Dispatch order to nearest emergency response team Response time under 10 minutes Delayed notification due to system failure Y N
1.2 Initiate Emergency Response Chief Dispatcher NetControl / CADx Dispatch order from Train Dispatcher Emergency response team dispatched Response team on scene within 30 minutes Inadequate resources for immediate response N Y
1.3 Secure the Scene Control Operator NetControl / CADx Emergency team report Scene secured and blocked off Scene secured within 60 minutes Difficulty in securing the scene due to weather conditions Y N
1.4 Coordinate with Emergency Services Train Dispatcher NetControl / CADx Emergency team report Coordination with local emergency services Coordination completed within 15 minutes Communication breakdown between railroad and emergency services N Y
1.5 Assess Damage Car Inspector (Carman) Umler / EHMS Scene secured report Damage assessment report Damage assessment completed within 2 hours Inaccurate damage assessment due to limited visibility Y N
1.6 Plan Recovery Operations VP Network Planning & Operations NetControl / CADx Damage assessment report Recovery operation plan Recovery plan finalized within 4 hours Resource allocation conflicts with other operations N Y
1.7 Implement Recovery Operations Train Dispatcher NetControl / CADx Recovery operation plan Recovery operations initiated Operations started within 1 hour of plan approval Logistical challenges in executing recovery plan Y N
1.8 Monitor Recovery Progress Control Operator NetControl / CADx Recovery operations status Progress report to Chief Dispatcher Progress updates every 30 minutes Inconsistent progress reporting N Y
1.9 Evaluate and Adjust Recovery Plan Chief Dispatcher NetControl / CADx Progress report Adjusted recovery plan if necessary Plan adjustments made within 2 hours of initial evaluation Difficulty in adjusting plans due to unforeseen issues Y N
1.10 Complete Recovery Operations Train Dispatcher NetControl / CADx Final progress report Recovery operations completed and site cleared Operations completed within 24 hours of initial notification Prolonged recovery due to extensive damage N Y
1.11 Conduct Post-Event Review Service Design / Network Planning Analyst NetControl / CADx Recovery operations report Post-event review report Review completed within 7 days of event resolution Insufficient data for comprehensive review Y N
1.12 Update Safety Protocols VP Network Planning & Operations NetControl / CADx Post-event review report Updated safety protocols Protocols updated within 30 days of event resolution Resistance to protocol changes from operational teams N Y
📊 KPIs & Risk Register

KPIs

Response time under 10 minutes Scene secured within 60 minutes Coordination completed within 15 minutes Damage assessment completed within 2 hours Recovery plan finalized within 4 hours Operations started within 1 hour of plan approval Progress updates every 30 minutes Plan adjustments made within 2 hours of initial evaluation Operations completed within 24 hours of initial notification Review completed within 7 days of event resolution Protocols updated within 30 days of event resolution

Key Risks

Inadequate resources for immediate response Difficulty in securing the scene due to weather conditions Communication breakdown between railroad and emergency services Resource allocation conflicts with other operations Logistical challenges in executing recovery plan Prolonged recovery due to extensive damage Insufficient data for comprehensive review Resistance to protocol changes from operational teams

Swim Lanes

Train Dispatcher · 1.1, 1.4, 1.6, 1.7, 1.9, 1.10 Chief Dispatcher · 1.2, 1.3, 1.8, 1.11, 1.12 Control Operator · 1.5, 1.10 Car Inspector (Carman) · 1.9