US Class I Rail Process Wiki Engineering: Track, Structures & Signals › PTC Wayside Assets and Subdivision Track Data File Management
🗺 BPMN Process Flow
RR-06-07-01 BPMN Diagram

Click diagram to zoom & pan • Scroll to zoom • Drag to pan • Download SVG

📋 Process Attributes
Process IDRR-06-07-01
Domain FamilyOPERATIONS
L1 DomainEngineering: Track, Structures & Signals
L2 Process GroupPTC Wayside Assets and Subdivision Track Data File Management
TriggerInitiated by a Track Supervisor upon detection of issues in PTC wayside assets or changes in the track layout that require updates to the data files.
OutcomeSuccessful completion results in accurate, up-to-date PTC wayside asset and subdivision track data files, ensuring safe train operations and compliance with regulations.
SystemsNetControl I-ETMS PTC Back Office Server (BOS) Umler EHMS
Regulatory Hooks49 CFR Part 213 49 CFR Part 236, Subpart I GCOR 6.28
📋 L4 Process Steps
StepNameRoleSystem InputOutputKPIPain Point / Risk Decision?Exception?
1.1 Identify Issues or Changes Track Supervisor NetControl Track inspection reports, maintenance logs Issue report Number of identified issues within 24 hours Delayed identification of critical track issues Y N
1.2 Prioritize Issues Track Supervisor NetControl Issue report Prioritized issue list Issues prioritized within 48 hours Overlooking critical issues due to poor prioritization Y N
1.3 Assign Maintenance Tasks Track Supervisor NetControl Prioritized issue list Maintenance task assignments Tasks assigned within 24 hours of prioritization Inefficient assignment leading to delayed maintenance Y N
1.4 Perform Maintenance Assistant Foreman (track) Umler, EHMS Maintenance task assignments Maintenance logs 95% completion rate of maintenance tasks within 7 days Equipment failure due to improper maintenance N Y
1.5 Update Data Files PTC Field Engineer / PTC Technician I-ETMS, PTC Back Office Server (BOS) Maintenance logs Updated PTC data files Data file updates completed within 3 days of maintenance Inaccurate data leading to operational disruptions Y N
1.6 Validate Data Files PTC Field Engineer / PTC Technician I-ETMS, PTC Back Office Server (BOS) Updated PTC data files Validation report 98% accuracy rate in validation reports Errors in data files causing safety risks Y N
1.7 Review Validation Reports Track Supervisor NetControl, I-ETMS Validation report Approval or rejection of data files Data file approval rate within 24 hours of validation Delayed approval leading to operational delays Y N
1.8 Deploy Updated Data Files PTC Field Engineer / PTC Technician I-ETMS, PTC Back Office Server (BOS) Approved data files Deployment logs 90% successful deployment rate within 48 hours of approval Data file deployment failures causing system downtime N Y
1.9 Monitor Deployment Track Supervisor NetControl, I-ETMS Deployment logs Monitoring report Continuous monitoring of deployed data files Undetected issues in deployed data files N Y
1.10 Report Findings Track Supervisor NetControl, I-ETMS Monitoring report Operational report Monthly reporting of operational findings Lack of comprehensive reporting N N
1.11 Review and Improve Chief Engineer / VP Engineering NetControl, I-ETMS Operational report Improvement plan 90% implementation rate of improvement plans within 6 months Ineffective implementation of improvement plans Y N
1.12 Close Process Track Supervisor NetControl, I-ETMS Improvement plan Process closure documentation Process closure within 7 days of improvement plan implementation Delayed process closure N Y
📊 KPIs & Risk Register

KPIs

Number of identified issues within 24 hours Issues prioritized within 48 hours Tasks assigned within 24 hours of prioritization 95% completion rate of maintenance tasks within 7 days Data file updates completed within 3 days of maintenance 98% accuracy rate in validation reports Data file approval rate within 24 hours of validation 90% successful deployment rate within 48 hours of approval Continuous monitoring of deployed data files Monthly reporting of operational findings 90% implementation rate of improvement plans within 6 months Process closure within 7 days of improvement plan implementation

Key Risks

Inaccurate data leading to operational disruptions Errors in data files causing safety risks Data file deployment failures causing system downtime Undetected issues in deployed data files Lack of comprehensive reporting Ineffective implementation of improvement plans Delayed process closure

Swim Lanes

Track Supervisor · 1.1, 1.2, 1.3, 1.7, 1.10 Assistant Foreman (track) · 1.4 PTC Field Engineer / PTC Technician · 1.5, 1.6, 1.8 Chief Engineer / VP Engineering · 1.11